Skip to main content
06-1998-0364Administrative - FormalClosedFY 1998· Region 06

EPA v. LEGNA LAND DEVELOPMENT CO., A TEXAS CORPORATION

Unilateral Administrative Order Without Adjudication

Compliance action

$4,000

Case summary

1. SECTION 309(A) OF THE CLEAN WATER ACT ( CWA ), 33 U.S.C. SECTION 1319(A). 2. LEGNA LAND DEVELOPMENT CO., A TEXAS CORPORATION FACILITY: A RESIDENTIAL DEVELOPMENT NORTHEAST CORNER OF FAIRMONT PARKWAY AND PECAN CROSSING LANE LA PORTE, HARRIS COUNTY, TEXAS 77571 3. RESPONDENT WAS IN VIOLATION OF SECTION 301 OF THE CWA BY CONDUCTING THE RELEVANT ACTIVITIES AND OPERATING THE FA- CILITY WITHOUT NPDES PERMIT COVERAGE. 4. RELIEF SOUGHT PURSUANT TO SECTION 309(A) OF THE CWA, EPA ISSUED AN ADMINISTRATIVE ORDER (AO) TO THE RESPONDENT. THE AO ORDERS THE RESPONDENT TO: A) WITHIN 30 DAYS OF THE EFFECTIVE DATE OF THE AO, MAKE A COMPLETE AND CORRECT AP- PLICATION FOR NPDES PERMIT COVERAGE, SUBMITTING A COPY OF THE APPLICATION, CONFIRMATION OF COVERAGE, AND THE PERMIT NUMBER TO EPA, B) WITHIN 30 DAYS OF THE AO, TAKE WHATEVER CORRECTIVE ACTION IS NECESSARY TO CORRECT THE DEFICIEN- CIES AND ELIMINATE AND PREVENT RECURRENCE OF THE VIOLA- TIONS CITED AND TO COME INTO COMPLIANCE WITH ALL OF THE APPLICABLE REQUIREMENTS OF THE PERMIT AND REGULATIONS, C) WITHIN 30 DAYS OF THE AO,SUBMIT A WRITTEN REPORT DETAIL- ING THE SPECIFIC ACTIONS TAKEN TO CORRECT THE VIOLATIONS, EXPLAINING WHY SUCH ACTIONS ARE ANTICIPATED TO BE SUFFIC- IENT TO PREVENT RECURRENCE OF THE VIOLATIONS, AND INCLUDE A COPY OF THE STORM WATER POLLUTION PREVENTION PLAN (SWPPP) PREPARED IN ACCORDANCE WITH PERMIT REQUIREMEMTS, D) IF RESPONDENT BELIEVES COMPLETE CORRECTION OF THE VIO- LATIONS IS NOT POSSIBLE WITHIN 30 DAYS, WITHIN 30 DAYS OF THE AO, SUBMIT A COMPREHENSIVE WRITTEN PLAN FOR ELIMINA- TION AND PREVENTION OF VIOLATIONS IN THE SHORTEST TIME POSSIBLE, AND E) WITHIN 45 DAYS OF THE AO, ARRANGE TO MEET WITH EPA AND SHOW CAUSE.

Defendants (1)

  • LEGNA LAND DEVELOPMENT CO.Named in complaintNamed in settlement

Facilities (1)

  • LEGNA LAND DEVELOPMENT CO.

    NE CORNER FAIRMONT PKY AND PECAN CROSSING LANE, LA PORTE, TX, 77571

    Registry ID: 110010734606

Statutes cited

  • CWA 301NPDES Discharge without a Permit

Enforcement conclusions (1)

  • LEGNA LAND DEVELOPMENT CO.entered 1998-03-20

    Primary law: CWA

Timeline (5 milestones)

  • 1998-03-20Final Order Issued
  • 1998-03-20Complaint Filed/Proposed Order
  • 1998-04-07Enforcement Action Data Entered
  • 2000-06-06Compliance Achieved
  • 2000-06-06Enforcement Action Closed

Case metadata

EPA activity ID
38058
Case number
06-1998-0364
Lead agency
EPA
HQ division
WAT
Branch
6EN-L
EPA region
06
Multimedia
No
Voluntary self-disclosure
No
Primary statute
NPDES Discharge without a Permit

Sourced verbatim from EPA ECHO Enforcement Case Report for case 06-1998-0364 . Bulk data: ICIS-FEC download summary.

This is legal information, not legal advice. Laws vary by jurisdiction and change frequently. Always verify current law with official sources and consult a licensed attorney in your jurisdiction for advice on your specific situation.