EPA v. CENTRAL ABATEMENT CO., INC.

Final Order With Penalty

Penalty assessed

$19,000

Case summary

FAILURE TO WET RACM DURING REMOVAL FROM THE FACILITY PRIOR TO DEMOLITION; FAILURE TO PREVENT VISIBLE EMISSIONS DURING REMOVAL OF ASBESTOS.

Defendants (3)

  • OLSHAN DEMOLISHING CO., INC.Named in complaintNamed in settlement
  • CENTEX BATESON CONSTRUCTION COMPANY, INCNamed in complaintNamed in settlement
  • CENTRAL ABATEMENT CO., INC.Named in complaintNamed in settlement

Statutes cited

  • CAA 112Hazardous Air Pollutants

Enforcement conclusions (1)

  • CENTRAL ABATEMENT CO., INC.entered 1993-12-17

    Primary law: CAA

    Federal penalty: $19,000

Timeline (6 milestones)

  • 1992-05-20Complaint Filed/Proposed Order
  • 1992-07-08Enforcement Action Data Entered
  • 1993-08-31Admin Law Judge Decision
  • 1993-12-17Final Order Issued
  • 1993-12-17Compliance Achieved
  • 1993-12-17Enforcement Action Closed

Case metadata

EPA activity ID
35441
Case number
06-1992-0095
Lead agency
EPA
HQ division
AIR
Branch
6C-AA
EPA region
06
Multimedia
No
Voluntary self-disclosure
No
Primary statute
Hazardous Air Pollutants