EPA v. Swinerton Builders, Prairie State Solar LLC, and Big River Solar LLC
Case summary
EPA alleges that the Defendants identified above violated a State-issued CWA Construction General Permit while constructing two solar energy production facilities in Illinois.
Defendants (3)
- Swinerton Builders
- Prairie State SolarNamed in complaintNamed in settlement
- Big River Solar LLCNamed in complaintNamed in settlement
Facilities (2)
PRAIRIE STATE SOLAR LLC
GOLDENROD ROAD AND TIGERLILY ROAD, PERRY COUNTY, IL, 62832
Registry ID: 110070945847
SWINERTON BUILDERS
COUNTY ROAD 1200 NORTH AND COUNTY ROAD 400 EAST, ENFIELD TOWNSHIP, IL, 62835
Registry ID: 110070948325
Statutes cited
- CWA 301/402 — NPDES Permit Violations
Enforcement conclusions (2)
Prairie State Solar LLCentered 2023-01-27
Primary law: CWA
Federal penalty: $159,398 · State/local: $67,500
Big River Solar LLCentered 2023-01-24
Primary law: CWA
Federal penalty: $122,500 · State/local: $52,500
Timeline (5 milestones)
- 2021-09-27Enforcement Action Data Entered
- 2021-09-27Referred To Dept Of Justice
- 2022-11-14Complaint Filed With Court
- 2023-01-27Final Order Lodged
- 2023-01-27Final Order Entered
Case metadata
- EPA activity ID
- 3602835164
- Case number
- 05-2021-0326
- Lead agency
- EPA
- EPA region
- 05
- Voluntary self-disclosure
- No
- Primary statute
- NPDES Permit Violations
Sourced verbatim from EPA ECHO Enforcement Case Report for case 05-2021-0326 . Bulk data: ICIS-FEC download summary.