05-2017-1002JudicialFinal Order EnteredFY 2017· Region 05
EPA v. ASHLAND/NORTHERN STATES POWER SITE - CONSENT DECREE (CERCLA)
Case summary
CD for reimbursement of costs incurred by EPA and US DOJ for response actions at the Ashland/Northern States Power Lakefront Site
Defendants (1)
- Northern States Power CompanyNamed in complaintNamed in settlement
Facilities (1)
ASHLAND/NORTHERN STATES POWER LAKEFRONT
300 ST. CLAIRE ST., ASHLAND, WI, 54806
Registry ID: 110009319558
Statutes cited
- CERCLA 107A — Cost Recovery
- CERCLA 106A — Imminent & Substantial Endangerment Order
Enforcement conclusions (1)
ASHLAND/NORTHERN STATES POWER SITE - CONSENT DECREE (CERCLA)entered 2017-03-01
Primary law: CERCLA
Timeline (5 milestones)
- 2016-12-28Referred To Dept Of Justice
- 2017-01-10Final Order Lodged
- 2017-01-10Complaint Filed With Court
- 2017-03-01Final Order Entered
- 2017-03-02Enforcement Action Data Entered
Case metadata
- EPA activity ID
- 3600972411
- Case number
- 05-2017-1002
- Lead agency
- EPA
- EPA region
- 05
- Voluntary self-disclosure
- No
- Primary statute
- Cost Recovery
Sourced verbatim from EPA ECHO Enforcement Case Report for case 05-2017-1002 . Bulk data: ICIS-FEC download summary.
This is legal information, not legal advice. Laws vary by jurisdiction and change frequently. Always verify current law with official sources and consult a licensed attorney in your jurisdiction for advice on your specific situation.