EPA v. TITTABAWASSEE RIVER - ADMIN SETTLEMENT AGREEMENT AND ORDER ON CONSENT (CERCLA)

Case summary

This Administrative Settlement Agreement and Order on Consent is entered into voluntarily by the United States Environmental Protection Agency (U.S. EPA) and The Dow Chemical Company. This agreement provides for Dow's performance of a non-time critical removal action selected by U.S. EPA. and the payment of certain response costs incurred by the United States oat or in connection with addressing sediment and riverbank soil contaminated with dioxins and furans within Segment 3 of the Tittabawassee River, Saginaw River & Bay site.

Defendants (1)

  • Neil C. HawkinsNamed in settlement

Facilities (1)

  • TITTABAWASSEE RIVER

    DOW DAM TO SAGINAW RIVER, MIDLAND, MI, 48640

    Registry ID: 110030826694

Statutes cited

  • CERCLA 106AImminent & Substantial Endangerment Order

Enforcement conclusions (1)

  • TITTABAWASSEE RIVER - ADMIN SETTLEMENT AGREEMENT AND ORDER ON CONSENT (CERCLA)entered 2016-02-25

    Primary law: CERCLA

Timeline (2 milestones)

  • 2016-02-25Final Order Issued
  • 2016-03-02Enforcement Action Data Entered

Case metadata

EPA activity ID
3600658440
Case number
05-2016-1004
Lead agency
EPA
EPA region
05
Voluntary self-disclosure
No
Primary statute
Imminent & Substantial Endangerment Order

Sourced verbatim from EPA ECHO Enforcement Case Report for case 05-2016-1004 . Bulk data: ICIS-FEC download summary.

This is legal information, not legal advice. Laws vary by jurisdiction and change frequently. Always verify current law with official sources and consult a licensed attorney in your jurisdiction for advice on your specific situation.