EPA v. CALUMET AND HECLA POWER PLANT ADMIN ORDER ON CONSENT (CERCLA)
Case summary
This Administrative Settlement Agreement and Order on Consent ( Settlement Agreement ) is entered into voluntarily by the United States Environmental Protection Agency and Respondent Honeywell Specialty Materials, LLC. This Settlement Agreement provides for the performance of removal actions by Honeywell in connection with the property located at 5371 Highway M-26 in Lake Linden, Torch Lake Township, Houghton County, Michigan, the Former Calumet & Hecla, Inc. Power Plant Superfund Site.
Defendants (1)
- HONEYWELL SPECIALTY MATERIALS, LLCNamed in settlement
Facilities (1)
CALUMET AND HECLA POWER PLANT SITE
HIGHWAY M-26 SOUTH OF THE VILLAGE OF, TORCH LAKE TOWNSHIP, MI, 49934
Registry ID: 110043687374
Statutes cited
- CERCLA 122H — Administrative Cost Recovery Settlement
- CERCLA 107A — Cost Recovery
- CERCLA 104E2 — Information and/or Access
- CERCLA 106A — Imminent & Substantial Endangerment Order
Enforcement conclusions (1)
CALUMET AND HECLA POWER PLANT ADMIN ORDER ON CONSENT (CERCLA)entered 2012-05-18
Primary law: CERCLA
Timeline (2 milestones)
- 2012-05-18Final Order Issued
- 2012-07-10Enforcement Action Data Entered
Case metadata
- EPA activity ID
- 3000036562
- Case number
- 05-2012-1017
- Lead agency
- EPA
- EPA region
- 05
- Voluntary self-disclosure
- No
- Primary statute
- Administrative Cost Recovery Settlement
Sourced verbatim from EPA ECHO Enforcement Case Report for case 05-2012-1017 . Bulk data: ICIS-FEC download summary.