Skip to main content
05-2012-1017Administrative - FormalFinal Order IssuedFY 2012· Region 05

EPA v. CALUMET AND HECLA POWER PLANT ADMIN ORDER ON CONSENT (CERCLA)

Case summary

This Administrative Settlement Agreement and Order on Consent ( Settlement Agreement ) is entered into voluntarily by the United States Environmental Protection Agency and Respondent Honeywell Specialty Materials, LLC. This Settlement Agreement provides for the performance of removal actions by Honeywell in connection with the property located at 5371 Highway M-26 in Lake Linden, Torch Lake Township, Houghton County, Michigan, the Former Calumet & Hecla, Inc. Power Plant Superfund Site.

Defendants (1)

  • HONEYWELL SPECIALTY MATERIALS, LLCNamed in settlement

Facilities (1)

  • CALUMET AND HECLA POWER PLANT SITE

    HIGHWAY M-26 SOUTH OF THE VILLAGE OF, TORCH LAKE TOWNSHIP, MI, 49934

    Registry ID: 110043687374

Statutes cited

  • CERCLA 122HAdministrative Cost Recovery Settlement
  • CERCLA 107ACost Recovery
  • CERCLA 104E2Information and/or Access
  • CERCLA 106AImminent & Substantial Endangerment Order

Enforcement conclusions (1)

  • CALUMET AND HECLA POWER PLANT ADMIN ORDER ON CONSENT (CERCLA)entered 2012-05-18

    Primary law: CERCLA

Timeline (2 milestones)

  • 2012-05-18Final Order Issued
  • 2012-07-10Enforcement Action Data Entered

Case metadata

EPA activity ID
3000036562
Case number
05-2012-1017
Lead agency
EPA
EPA region
05
Voluntary self-disclosure
No
Primary statute
Administrative Cost Recovery Settlement

Sourced verbatim from EPA ECHO Enforcement Case Report for case 05-2012-1017 . Bulk data: ICIS-FEC download summary.

This is legal information, not legal advice. Laws vary by jurisdiction and change frequently. Always verify current law with official sources and consult a licensed attorney in your jurisdiction for advice on your specific situation.