Skip to main content
05-2011-1018Administrative - FormalFinal Order IssuedFY 2011· Region 05

EPA v. WPSC CAMP MARINA MGP ADMIN ORDER ON CONSENT (CERCLA)

Case summary

This Administrative Settlement Agreement and Order on Consent is entered into voluntarily by the U.S. Environmental Protection Agency and Wisconsin Public Service Corporation (WPSC). This Settlement Agreement provides for the performance of a removal action by Respondent at or in connection with the WPSC Campmarina MGP Site generally located in Sheboygan, Wisconsin. This Settlement Agreement is issued under the authority vested in the President of the United States by Sections 104, 106(a), 107 and 122 of the Comprehensive Environmental Response, Compensation and Liability Act of 1980, 42 U.S.C. §§ 9604, 9606(a), 9607 and 9622, as amended (CERCLA).

Defendants (1)

  • Wisconsin Public Service CorporationNamed in settlement

Facilities (1)

  • WPSC CAMP MARINA MGP

    732 NORTH WATER ST, SHEBOYGAN, WI, 53081

    Registry ID: 110024424880

Statutes cited

  • CERCLA 122HAdministrative Cost Recovery Settlement
  • CERCLA 104E2Information and/or Access
  • CERCLA 107ACost Recovery
  • CERCLA 106AImminent & Substantial Endangerment Order

Enforcement conclusions (1)

  • WPSC CAMP MARINA MGP ADMIN ORDER ON CONSENT (CERCLA)entered 2011-06-23

    Primary law: CERCLA

Timeline (2 milestones)

  • 2011-06-23Final Order Issued
  • 2011-07-06Enforcement Action Data Entered

Case metadata

EPA activity ID
2600033690
Case number
05-2011-1018
Lead agency
EPA
EPA region
05
Voluntary self-disclosure
No
Primary statute
Administrative Cost Recovery Settlement

Sourced verbatim from EPA ECHO Enforcement Case Report for case 05-2011-1018 . Bulk data: ICIS-FEC download summary.

This is legal information, not legal advice. Laws vary by jurisdiction and change frequently. Always verify current law with official sources and consult a licensed attorney in your jurisdiction for advice on your specific situation.