EPA v. XCEL ENERGY CORPORATION
Final Order With Penalty
Case summary
XCEL ENERGY FAILED TO COMPLY WITH INFORMATION REQUEST ISSUED UNDER SECTION 114(A) ON JULY 27, 2009, CONCERNING TWO MINNESOTA POWER PLANTS.
Defendants (1)
- XCEL ENERGY CORPORATIONNamed in complaintNamed in settlement
Facilities (2)
NSP/XCEL ENERGY BLACK DOG GENERATING
1400 BLACK DOG RD, BURNSVILLE, MN, 553371218
Registry ID: 110017409320
XCEL ENERGY - SHERBURNE COUNTY GENERATING PLANT
13999 INDUSTRIAL BLVD, BECKER, MN, 553088800
Registry ID: 110000424700
Statutes cited
- CAA 114 — Record keeping, Inspection, Information Request
Enforcement conclusions (1)
XCEL ENERGY CORPORATIONentered 2010-12-13
Primary law: CAA
Federal penalty: $35,000
Timeline (6 milestones)
- 2010-03-31Referred To Dept Of Justice
- 2010-04-05Enforcement Action Data Entered
- 2010-06-07Complaint Filed With Court
- 2010-12-13Final Order Lodged
- 2010-12-13Final Order Entered
- 2012-01-05Enforcement Action Closed
Case metadata
- EPA activity ID
- 1800089958
- Case number
- 05-2010-2701
- Lead agency
- EPA
- EPA region
- 05
- Voluntary self-disclosure
- No
- Primary statute
- Record keeping, Inspection, Information Request
Sourced verbatim from EPA ECHO Enforcement Case Report for case 05-2010-2701 . Bulk data: ICIS-FEC download summary.
This is legal information, not legal advice. Laws vary by jurisdiction and change frequently. Always verify current law with official sources and consult a licensed attorney in your jurisdiction for advice on your specific situation.