EPA v. NIPSCO BAILLY GENERATING STATION
Case summary
The Northern Indiana Public Service Company (NIPSCO) and Region 5 entered into an Administrative Order on Consent to clean up past releases under RCRA Section 3008(h) on March 31, 2005. This is a streamlined corrective action agreement covering the Bailly Generating Station in Chesterton, Indiana, which is included in the RCRA Cleanup Baseline for 2008 under the GPRA. The facility is a coal-fired power plant, and is located adjacent to the Indiana Dunes National Lakeshore. NIPSCO will investigate and correct past releases of cadmium, chromium, and lead.
Defendants (1)
- NIPSCO BAILLY GENERATING STATIONNamed in complaintNamed in settlement
Facilities (1)
NIPSCO BAILLY GENERATING STATION
246 BAILLY STATION ROAD, CHESTERTON, IN, 46304-9780
Registry ID: 110000397730
Statutes cited
- RCRA 3008H — Interim Status Corrective Action Order
Enforcement conclusions (1)
NIPSCO BAILLY GENERATING STATIONentered 2005-03-31
Primary law: RCRA
Timeline (2 milestones)
- 2005-03-31Final Order Issued
- 2005-04-05Enforcement Action Data Entered
Case metadata
- EPA activity ID
- 143146
- Case number
- 05-2005-9903
- Lead agency
- EPA
- Branch
- CAS
- EPA region
- 05
- Voluntary self-disclosure
- No
- Primary statute
- Interim Status Corrective Action Order
Sourced verbatim from EPA ECHO Enforcement Case Report for case 05-2005-9903 . Bulk data: ICIS-FEC download summary.
This is legal information, not legal advice. Laws vary by jurisdiction and change frequently. Always verify current law with official sources and consult a licensed attorney in your jurisdiction for advice on your specific situation.