A RCRA CEI was accomplished on 12/8/2003. An NOV was isssue to Circuit on 8/24/2004 for violations of the contingency plan requirements, training requirements, manifesting requirements, notification requirements, and tank requirements. A show cause meeting was conducted on 12/22/2004. Based on several documents submitted by Circuit to the US EPA throughout the enforcement process, the penalty was assessed at $8,321. A 10% reduction was given to Circuit based on their good faith efforts and cooperation to come into compliance prior to the issuance of this CAFO.The final assessed penalty was calculated at $7,489.
Defendants (1)
- CIRCUIT ENGINEERING LLCNamed in complaintNamed in settlement
Facilities (1)
CIRCUIT ENGINEERING LLC
511 VISTA AVENUE, ADDISON, IL, 60101
Registry ID: 110018483327
Statutes cited
- RCRA 3004 — Hazardous Waste Treatment, Storage, and Disposal Standards
- RCRA 3002 — Standards Applicable to Generators of Hazardous Waste
Enforcement conclusions (1)
CIRCUIT ENGINEERING LLCentered 2005-04-27
Primary law: RCRA
Federal penalty: $7,489
Timeline (3 milestones)
- 2005-04-27Complaint Filed/Proposed Order
- 2005-04-27Final Order Issued
- 2005-04-28Enforcement Action Data Entered
Case metadata
- EPA activity ID
- 146458
- Case number
- 05-2005-9901
- Lead agency
- EPA
- Branch
- ECAB
- EPA region
- 05
- Voluntary self-disclosure
- No
- Primary statute
- Hazardous Waste Treatment, Storage, and Disposal Standards