EPA v. Warren Wastewater Treatment Plant
Final Order With Penalty
Case summary
On September 20, 2004, Warren Wastewater Treatment Plant in Warren, MI was inspected to determine whether the facility was complying with the Risk Management Program regulations. The facility submitted an initial RMP on June 15, 1999. They resubmitted their update on June 17, 2004. The inspector found that the facility failed to implement their RMP Program. Some of the more serious violations include not completing a compliance audit, not maintaining records for both the worst case and alternative case release scenarios, and not implementing management of change procedures. A $6975 penalty is being sought.
Defendants (1)
- Warren Wastewater Treatment PlantNamed in complaintNamed in settlement
Facilities (1)
WARREN WASTEWATER TREATMENT PL
32360 WARKOP AVENUE, WARREN, MI, 48093-1084
Registry ID: 110000759965
Statutes cited
- CAA 112[R][7] — Prevention of Accidental Release/Risk Management Plans (RMPs)
Enforcement conclusions (1)
Warren Wastewater Treatment Plantentered 2005-02-08
Primary law: CAA
Federal penalty: $6,975
Timeline (7 milestones)
- 2004-12-16Expedited Settlement Offered
- 2005-02-08Complaint Filed/Proposed Order
- 2005-02-08Final Order Issued
- 2005-02-08Compliance Achieved
- 2005-02-08Pipeline Closed
- 2005-02-08Enforcement Action Closed
- 2005-02-15Enforcement Action Data Entered
Case metadata
- EPA activity ID
- 139668
- Case number
- 05-2005-3606
- Lead agency
- EPA
- EPA region
- 05
- Voluntary self-disclosure
- No
- Primary statute
- Prevention of Accidental Release/Risk Management Plans (RMPs)
Sourced verbatim from EPA ECHO Enforcement Case Report for case 05-2005-3606 . Bulk data: ICIS-FEC download summary.
This is legal information, not legal advice. Laws vary by jurisdiction and change frequently. Always verify current law with official sources and consult a licensed attorney in your jurisdiction for advice on your specific situation.