EPA v. ALCHEM ALUMINUM, INC.
Final Order No Penalty
Case summary
ALCHEM ALUMINUM FAILED TO CONDUCT STACK TESTING FOR DIOXIN WITHIN 180 DAYS OF STARTUP OF ITS SMELTING FURNACE, AS REQUIRED BY THE SECONDARY ALUMINUM NESHAP. THE FURNACE WAS TAKEN DOWN FOR REPAIRS, AND WILL BE TESTED WITHIN 30 DAYS OF RE-STARTING.
Defendants (1)
- ALCHEM ALUMINUM, INC.Named in settlement
Facilities (1)
ALCHEM ALUMINUM, INC.
NODULAR DRIVE, SAGINAW, MI, 48601
Registry ID: 110008058305
Statutes cited
- CAA 112 — Hazardous Air Pollutants
Enforcement conclusions (1)
ALCHEM ALUMINUM, INC.entered 2001-09-10
Primary law: CAA
Timeline (3 milestones)
- 2001-09-10Final Order Issued
- 2001-10-01Enforcement Action Closed
- 2001-10-03Enforcement Action Data Entered
Case metadata
- EPA activity ID
- 33242
- Case number
- 05-2001-0617
- Lead agency
- EPA
- HQ division
- AIR
- Branch
- MMBI
- EPA region
- 05
- Multimedia
- No
- Voluntary self-disclosure
- No
- Primary statute
- Hazardous Air Pollutants
Sourced verbatim from EPA ECHO Enforcement Case Report for case 05-2001-0617 . Bulk data: ICIS-FEC download summary.