Case summary

THE RESPONDENT ARVIN MERITOR INC. SHALL PERFORM THE FOLLOW- ING RESPONSE ACTIVITIES: GENERATE A WORK PLAN, A HEALTH & SAFETY PLAN, A SAMPLING AND QA/QC PLAN AND AN AIR MONITORING PLAN; ESTABLISH AND MAINTAIN SITE SECURITY; PERFORM SOIL SAMPLING AND CHEMICAL ANALYSIS; REMOVE CONTAMINATED SOIL FROM THE RESIDENTIAL, AND SO ON. RESPONDENT SHALL REIMBURSE U.S. EPA FOR ALL RESPONSE COSTS INCURRED BY THE UNITED STATES IN OVERSEEING RESPONDENT'S IMPLEMENTATION OF THE REQUIREMENTS OF THIS ORDER. VIOLATION OF ANY PROVISION OF THIS ORDER MAY SUBJECT RESPONDENT TO CIVIL PENALTIES OF UP TO $27,500 PER VIOLATION PER DAY.

Defendants (2)

  • ARVIN MERITOR, INC.
  • ROCKWELL INTERNATIONAL SITENamed in settlement

Facilities (1)

  • ROCKWELL INTERNATIONAL CORP

    1 GLASS ST, ALLEGAN, MI, 49010

    Registry ID: 110003583907

Statutes cited

  • CERCLA 106AImminent & Substantial Endangerment Order

Enforcement conclusions (1)

  • ROCKWELL INTERNATIONALentered 2001-08-09

    Primary law: CERCLA

Timeline (2 milestones)

  • 2001-08-09Final Order Issued
  • 2001-08-28Enforcement Action Data Entered

Case metadata

EPA activity ID
33201
Case number
05-2001-0575
Lead agency
EPA
HQ division
CER
Branch
MMBI
EPA region
05
Multimedia
No
Voluntary self-disclosure
No
Primary statute
Imminent & Substantial Endangerment Order

Sourced verbatim from EPA ECHO Enforcement Case Report for case 05-2001-0575 . Bulk data: ICIS-FEC download summary.

This is legal information, not legal advice. Laws vary by jurisdiction and change frequently. Always verify current law with official sources and consult a licensed attorney in your jurisdiction for advice on your specific situation.