EPA v. ZIONSVILLE THIRD SITE
Final Order With Specified Cost Recovery
Cost recovery
$28,102
Case summary
THIS CASE INCLUDES AN ADMINISTRATIVE ORDER BY CONSENT AGREED TO BY THE PRPS AND EPA TO CONDUCT AN ENGINEERING EVALUATION/COS ANALYSIS (EE/CA) AT ZIONSVILLE THIRD SITE IN ANTICIPATION OF A FUTURE NON-TIME CRITICAL REMOVAL ACTION. A DE MINIMIS SETTLEMENT IS ALSO INCLUDED AS PART OF THE CASE WHEREIN 222 DE MINIMIS SETTLORS HAVE AGREED TO PAY A TOTAL OF $1,504,754 INTO AN ENCROW ACCOUNT TO BE HELD FOR PAYMENT OF U.S. EPA'S RESPONSE COSTS AND FOR FUNDING THE REMOVAL ACTION TO BE PERFORMED LATER AT THE SITE. IN ADDITION, 102 NON DE MINIMIS SETTLORS HAVE AGREED TO PAY $28,102.59 TO REIMBURSE ALL OF U.S. EPA'S PAST RESPONSE COSTS.
Defendants (1)
- ZIONSVILLE THIRD SITENamed in settlement
Facilities (1)
THIRD SITE
985 S SR 421, ZIONSVILLE, IN, 46077
Registry ID: 110009569430
Statutes cited
- CERCLA 122G — Administrative De Minimis Settlement
Enforcement conclusions (1)
ZIONSVILLE THIRD SITEentered 1999-05-03
Primary law: CERCLA
Timeline (2 milestones)
- 1999-05-03Final Order Issued
- 1999-05-10Enforcement Action Data Entered
Case metadata
- EPA activity ID
- 31624
- Case number
- 05-1999-0283
- Lead agency
- EPA
- HQ division
- CER
- Branch
- MMBII
- EPA region
- 05
- Multimedia
- No
- Voluntary self-disclosure
- No
- Primary statute
- Administrative De Minimis Settlement
Sourced verbatim from EPA ECHO Enforcement Case Report for case 05-1999-0283 . Bulk data: ICIS-FEC download summary.
This is legal information, not legal advice. Laws vary by jurisdiction and change frequently. Always verify current law with official sources and consult a licensed attorney in your jurisdiction for advice on your specific situation.