Skip to main content
05-1998-0565Administrative - FormalClosedFY 1998· Region 05

EPA v. UNITED HARD CHROME CORPORATION

Final Order With Penalty

Penalty assessed

$6,177

Compliance action

$25,000

Case summary

ADMINISTRATIVE PENALTY PROCEEDING, UNITED FAILED TO PERFORM INITIAL PERFORMANCE TESTING FOR ITS EIGHT HARD CHROME PLATING TANKS BY THE REGULATORY DEADLINE OF JULY 25, 1997. THIS IS A VIOLATION OF 40 C.F.R. 63.7 (A) (2). THE FACILITY'S PLATING TANKS WERE REQUIRED TO BE TESTED WITHIN 180 DAYS OF THE COMPLIANCE DATE--BY JULY 25, 1997. UNITED TESTED THE TANKS ABOUT 9 MONTHS AFTER THE DEADLINE (THE TESTS INDICATED COMPLIANCE WITH THE CHROME EMISSIONS LIMIT). SINCE THE TANKS WERE NOT TESTED BY THE TESTING DEADLINE, UNITED WAS IN VIOLATION OF 63.7 (A) (2).

Defendants (1)

  • UNITED HARD CHROME CORPORATIONNamed in complaintNamed in settlement

Facilities (1)

  • UNITED HARD CHROME CORPORATION

    2202 GILBERT AVENUE, NE, CANTON, OH, 44705

    Registry ID: 110001630281

Statutes cited

  • CAA 112Hazardous Air Pollutants

Enforcement conclusions (1)

  • UNITED HARD CHROME CORPORATIONentered 1998-12-10

    Primary law: CAA

    Federal penalty: $6,177

Timeline (4 milestones)

  • 1998-09-29Complaint Filed/Proposed Order
  • 1998-09-30Enforcement Action Data Entered
  • 1998-12-10Final Order Issued
  • 1999-02-25Enforcement Action Closed

Case metadata

EPA activity ID
31151
Case number
05-1998-0565
Lead agency
EPA
HQ division
AIR
Branch
MMBII
EPA region
05
Multimedia
No
Voluntary self-disclosure
No
Primary statute
Hazardous Air Pollutants

Sourced verbatim from EPA ECHO Enforcement Case Report for case 05-1998-0565 . Bulk data: ICIS-FEC download summary.

This is legal information, not legal advice. Laws vary by jurisdiction and change frequently. Always verify current law with official sources and consult a licensed attorney in your jurisdiction for advice on your specific situation.