Case summary

THIS IS AN ONGOING FILL AND WE NEED AN ATTORNEY ASSIGNMENT WHERE THE ATTORNEY CAN TURN AROUND THIS WITHIN 1 WEEK. IT WAS REPORTED TO US ON 6/5/98 THAT ADDITIONAL WORK IS CON- TINUING ON SITE. THIS IS A PRIORITY CASE FOR THE WETLAND PROGRAM AND A POTENTIAL REFERRAL CANDIDATE FOR FY 98. THE SITE IS IN LAKE STATION (LAKE COUNTY) INDIANA. IT IS ESSENTIALLY A NATURAL WETLANDS FIELD AND SLIGHT HILLSIDE THAT THE PUTATIVE SITE OWNER (MR. ROWLAND FABIAN) IS ALLEGED TO HAVE ALTERED WITH HEAVY EARTH-MOVING CONSTRUCTION EQUIPMENT, IN MARCH AND/OR APRIL 1998, PROBABLY FOR COMMERCIAL DEVELOPMENT PURPOSES. THE ARMY CORP OF ENGINEERS IS ALSO LOOKING INTO THE SITE, AND HAS ISSUED A SEPARATE ORDER (BUT MAY NOT HAVE THE SAME DEGREE OF ADMINISTRATIVE AUTHORITY THAT WE HAVE).

Defendants (1)

  • FABIAN_ROWLANDNamed in complaintNamed in settlement

Facilities (1)

  • FABIAN SITE

    STATE ROUTE 20, LAKE STATION, IN, 46405

    Registry ID: 110010727507

Statutes cited

  • CWA 309Violation of Existing AO

Enforcement conclusions (1)

  • FABIAN ROWLANDentered 1998-06-25

    Primary law: CWA

Timeline (2 milestones)

  • 1998-06-17Enforcement Action Data Entered
  • 1998-06-25Final Order Issued

Case metadata

EPA activity ID
30826
Case number
05-1998-0174
Lead agency
EPA
HQ division
WAT
Branch
MMBI
EPA region
05
Multimedia
No
Voluntary self-disclosure
No
Primary statute
Violation of Existing AO