Skip to main content
05-1992-0223Administrative - FormalClosedFY 1992· Region 05

EPA v. COMMONWEALTH EDISON CO.

Final Order With Penalty

Penalty assessed

$9,250

Case summary

IN JULY, 1990, A POLE-MOUNTED TRANSFORMER OWNED BY RESPONDENT, COMMONWEALTH EDISON, FAILED, SPILLING FLUID ONTO STREET AND YARD. USEPA INSPECTED THE SPILL AREA IN DECEMBER 1990, FINDING THAT RESPONDENT HAD NOT CLEANED UP THE AREA. U.S. EPA IS ISSUING THIS COMPLAINT FOR RESPONDENT'S TSCA PCB DISPOSAL VIOLATION AND RESPONDENT'S FAILURE TO CLEAN UP THE SPILL AREA WITHIN 48 HOURS AS REQUIRED BY 40 C.F.R. S761.125.

Defendants (1)

  • COMMONWEALTH EDISON CO.Named in complaintNamed in settlement

Facilities (1)

  • COM ED GENERAL OFFICE

    72 W ADAMS ST, CHICAGO, IL, 60603

    Registry ID: 110033149475

Statutes cited

  • TSCA 6-PCBSPCBS

Enforcement conclusions (1)

  • COMMONWEALTH EDISON CO.entered 1993-02-26

    Primary law: TSCA

    Federal penalty: $9,250

Timeline (4 milestones)

  • 1992-09-04Enforcement Action Data Entered
  • 1993-02-26Final Order Issued
  • 1993-03-03Compliance Achieved
  • 1993-03-03Enforcement Action Closed

Case metadata

EPA activity ID
28054
Case number
05-1992-0223
Lead agency
EPA
HQ division
TOX
Branch
AWTGL
EPA region
05
Multimedia
No
Voluntary self-disclosure
No
Primary statute
PCBS

Sourced verbatim from EPA ECHO Enforcement Case Report for case 05-1992-0223 . Bulk data: ICIS-FEC download summary.

This is legal information, not legal advice. Laws vary by jurisdiction and change frequently. Always verify current law with official sources and consult a licensed attorney in your jurisdiction for advice on your specific situation.