EPA v. PAGEL'S PIT
Final Order No Penalty
Case summary
BY THIS LETTER, U.S. EPA, REGION V, TRANSMITS THE ATTACHED PRE-REFERRAL LITIGATION REPORT TO INITIATE REMEDIAL DESIGN AND REMEDIAL ACTION NEGOTIATIONS AT PAGEL'S PIT. 8/18/99 THE AGENCY ISSUED PROPOSED PLAN TO ADDRESS THE 1ST AND 2ND OPERABLE UNITS.
Defendants (1)
- WINNEBAGO RECLAMTION SERVICE, INC.Named in complaintNamed in settlement
Facilities (1)
PAGEL'S PIT
BAXTER & LINDENWOOD RD, ROCKFORD, IL, 61109
Registry ID: 110009283300
Statutes cited
- CERCLA 107A — Cost Recovery
Enforcement conclusions (1)
PAGEL'S PITentered 1993-02-10
Primary law: CERCLA
Timeline (7 milestones)
- 1990-09-30PRN Sent
- 1990-10-04Enforcement Action Data Entered
- 1992-09-29Referred To Dept Of Justice
- 1993-02-03Complaint Filed With Court
- 1993-02-10Final Order Lodged
- 1993-02-10Final Order Entered
- 1993-02-10Concluded
Case metadata
- EPA activity ID
- 27542
- Case number
- 05-1990-0262
- Lead agency
- EPA
- HQ division
- CER
- Branch
- SWERB
- EPA region
- 05
- Multimedia
- No
- Voluntary self-disclosure
- No
- Primary statute
- Cost Recovery
Sourced verbatim from EPA ECHO Enforcement Case Report for case 05-1990-0262 . Bulk data: ICIS-FEC download summary.