EPA v. J.D.R. CONSTRUCTION & DESIGN, INC
Final Order With Penalty
Case summary
8/14/2024 - EXPEDITED SETTLEMENT AGREEMENT ISSUED ASSESSING A PENALTY OF $ 8,223 PENALTY DUE WITHIN 15 DAYS. ALLEGED VIOLATIONS: BASED ON INFORMATION ACQUIRED FROM AN INFORMATION REQUEST LETTER THE EPA SENT VIA ELECTRONIC MAIL ON JUNE 5, 2024, REGARDING THE DEMOLITION ACTIVITY THAT OCCURRED AT 32 BULL STREET, SAVANNAH, GEORGIA 31401 (THE FACILITY), THE EPA ALLEGES THAT RESPONDENT VIOLATED SECTION 112 OF THE CAA, 42 U.S.C. ? 7412, AND 40 C.F.R. PART 61 SUBPART M. SPECIFICALLY, THE EPA ALLEGES THE RESPONDENT FAILED TO CONDUCT A THOROUGH INSPECTION FOR ASBESTOS-CONTAINING MATERIALS PRIOR TO BEGINNING DEMOLITION ACTIVITY, AS REQUIRED BY 40 C.F.R. ? 61.145(A), AND PROVIDE NOTICE OF INTENT TO DEMOLISH, AS REQUIRED BY 40 C.F.R. ? 61.145(B), AT THE FACILITY. THE DEMOLITION OCCURRED ON OR ABOUT JUNE 10, 2024.
Defendants (1)
- J.D.R. CONSTRUCTION & DESIGN, INCNamed in complaintNamed in settlement
Facilities (2)
32 BULL STREET (DEMOLITION SITE)
32 BULL STREET, SAVANNAH, GA, 31401
Registry ID: 110071721900
J.D.R. CONSTRUCTION & DESIGN, INC
208 EAST MONTGOMERY CROSS ROAD, SAVANNAH, GA, 31406
Registry ID: 110071819632
Statutes cited
- CAA 112B — Asbestos
Enforcement conclusions (1)
J.D.R. CONSTRUCTION & DESIGN, INCentered 2024-08-14
Primary law: CAA
Federal penalty: $8,223
Timeline (3 milestones)
- 2024-08-14Complaint Filed/Proposed Order
- 2024-08-14Final Order Issued
- 2024-08-28Enforcement Action Data Entered
Case metadata
- EPA activity ID
- 3604080327
- Case number
- 04-2024-0010
- Lead agency
- EPA
- EPA region
- 04
- Voluntary self-disclosure
- No
- Primary statute
- Asbestos
Sourced verbatim from EPA ECHO Enforcement Case Report for case 04-2024-0010 . Bulk data: ICIS-FEC download summary.
This is legal information, not legal advice. Laws vary by jurisdiction and change frequently. Always verify current law with official sources and consult a licensed attorney in your jurisdiction for advice on your specific situation.