04-2023-0603Administrative - FormalClosedFY 2023· Region 04
EPA v. Virginia Electric and Power Company Rosemary Power Station
Final Order With Penalty
Case summary
06/05/23-Consent Agreement issues. Assessing Penalty of $7738 to be paid within 30 days..
Defendants (3)
- Virginia Electric and Power CompanyNamed in complaintNamed in settlement
- Environmental and Sustainability
- Jason E.Williams, Vice President
Facilities (1)
ROSEMARY POWER STATION
120 WEST 12TH STREET, ROANOKE RAPIDS, NC, 27870-3713
Registry ID: 110001483261
Statutes cited
- EPCRA 313 — Toxic Chemical Release Reporting (TRI)
Enforcement conclusions (1)
Virginia Electric and Power Company Rosemary Power Stationentered 2023-06-05
Primary law: EPCRA
Federal penalty: $7,738
Timeline (4 milestones)
- 2023-06-05Final Order Issued
- 2023-06-05Complaint Filed/Proposed Order
- 2023-06-16Enforcement Action Closed
- 2023-07-11Enforcement Action Data Entered
Case metadata
- EPA activity ID
- 3603647334
- Case number
- 04-2023-0603
- Lead agency
- EPA
- EPA region
- 04
- Voluntary self-disclosure
- No
- Primary statute
- Toxic Chemical Release Reporting (TRI)
Sourced verbatim from EPA ECHO Enforcement Case Report for case 04-2023-0603 . Bulk data: ICIS-FEC download summary.