EPA v. EMERALD TRANSFORMER PPM LLC - TANK FARM
Final Order With Penalty
Case summary
9/12/2022- CONSENT AGREEMENT AND FINAL ORDER ISSUED ASSESSING A PENALTY OF $22,200. PENALTY TO BE PAID WITHIN 30 DAYS. ALLEGED VIOLATIONS: THE EPA ALLEGES THAT RESPONDENT FAILED TO IMMEDIATELY CLEAN UP ANY LEAKS AND/OR SPILLS OF PCB FLUIDS IN THE TANK FARM IN VIOLATION OF 40 C.F.R. ? 761.65, APPROVAL CONDITION B.11, AND SECTION 15 OF TSCA, 15 U.S.C. ? 2614. THE EPA ALLEGES THAT RESPONDENT FAILED TO HAVE A WRITTEN MAINTENANCE SCHEDULE OR RECORDS OF MAINTENANCE AND CLEANING ACTIVITIES IN VIOLATION OF APPROVAL CONDITION A.14.E AND SECTION 15 OF TSCA, 15 U.S.C. ? 2614.
Defendants (1)
- EMERALD TRANSFORMER PPM LLCNamed in complaintNamed in settlement
Facilities (1)
EMERALD TRANSFORMER PPM LLC
1875 FORGE ST, TUCKER, GA, 30084
Registry ID: 110000788808
Statutes cited
- TSCA 6-PCBS — PCBS
Enforcement conclusions (1)
EMERALD TRANSFORMER PPM LLC - Tank Farmentered 2022-09-12
Primary law: TSCA
Federal penalty: $22,200
Timeline (4 milestones)
- 2022-09-12Final Order Issued
- 2022-09-12Complaint Filed/Proposed Order
- 2022-09-19Enforcement Action Data Entered
- 2022-10-11Enforcement Action Closed
Case metadata
- EPA activity ID
- 3603357927
- Case number
- 04-2022-3202
- Lead agency
- EPA
- EPA region
- 04
- Voluntary self-disclosure
- No
- Primary statute
- PCBS
Sourced verbatim from EPA ECHO Enforcement Case Report for case 04-2022-3202 . Bulk data: ICIS-FEC download summary.
This is legal information, not legal advice. Laws vary by jurisdiction and change frequently. Always verify current law with official sources and consult a licensed attorney in your jurisdiction for advice on your specific situation.