Skip to main content
04-2018-5750Administrative - FormalFinal Order IssuedFY 2018· Region 04

EPA v. WALTON PLANTATION MASTER ASSOCIATION, INC.

Final Order No Penalty

Case summary

2/2/18 - ADMINISTRATIVE COMPLIANCE ORDER ON CONSENT ISSUED. ALLEGATIONS: ON JUNE 2, 2009, EPA CONDUCTED AN INSPECTION OF THE DISCHARGE AREA WITH THE U.S. ARMY CORPS OF ENGINEERS (COE) AND DETERMINED THAT FILL MATERIAL HAD BEEN PLACED IN WATERS OF THE U.S. W/OUT A PERMIT ISSUED UNDER CWA 404. UNION STATE BANK HELD A MORTGAGE ON THE REAL PROPERTY CONTAINING THE DISCHARGE AREA WHICH WAS IN DEFAULT. ON OR ABOUT MAY 17, 2017, RESPONDENT ACQUIRED OWNERSHIP OF THE DISCHARGE AREA VIA CERTIFICATE OF TITLE. RESPONDENT IS CURRENTLY THE OWNER AND/OR OPERATOR OF THE SITE, WHICH CONTAINS THE DISCHARGE AREA. AT NO TIME DURING THE DISCHARGE OF DREDGED AND/OR FILL MATERIAL INTO THE DISCHARGE AREA FROM ON OR ABOUT JUNE 27, 2006, TO THE PRESENT, DID RESPONDENT OR RESPONDENT'S PREDECESSOR POSSESS A PERMIT UNDER CWA 404. THE UNAUTHORIZED ACTIVITIES IMPACTED APPROX .42 ACRES OF WETLANDS THAT ARE ADJACENT TO AN UNNAMED PERENNIAL TRIBUTARY. THE UNNAMED TRIBUTARY FLOWS TO PINE LOG CREEK. PINE LOG CREEK IS A PERENNIAL TRIBUTARY OF POND CREEK. POND CREEK IS A PERENNIAL TRIBUTARY OF THE SHOAL RIVER, A NAVIGABLE-IN-FACT WATER OF THE U.S. AGREEMENT: RESPONDENT AGREES TO THE FOLLOWING: A. WITHIN 30 DAYS, RESPONDENT SHALL APPLY TO THE COE FOR AN AFTER-THE-FACT PERMIT AUTHORIZING APPROX .42 ACRES OF DREDGED AND/OR FILL MATERIAL THAT WILL REMAIN IN PLACE AT THE DISCHARGE AREA. IF THE AFTER-THE-FACT PERMIT IS GRANTED, RESPONDENT SHALL TIMELY COMPLY WITH ALL REQUIREMENTS AND CONDITIONS OF THE PERMIT. B. RESPONDENT SHALL PROVIDE A COPY OF ITS PERMIT APPLICATION TO EPA WITHIN 10 DAYS OF SUBMITTAL. C. RESPONDENT SHALL PROVIDE EPA A COPY OF THE COE PERMIT AUTHORIZATION, INCLUDING ANY CONDITIONS THERETO, IF GRANTED, WITHIN 10 DAYS OF ISSUANCE. D. WITHIN 30 DAYS, RESPONDENT SHALL RECORD A CERTIFIED COPY OF THIS AOC WITH THE RECORDER OF DEEDS IN THE APPROPRIATE COUNTY, ALONG WITH THE APPROVED DEED OF RESTRICTIVE COVENANTS, AND PROVIDE A COPY OF THE RECORDING TO EPA.

Defendants (1)

  • WALTON PLANTATION MASER ASSOCIATION, INC.Named in settlement

Facilities (1)

  • WETLANDS (WALTON PLANTATION)

    2231 COUNTY HIGHWAY 2, LAUREL HILL, FL, 32567

    Registry ID: 110038395607

Statutes cited

  • CWA 301NPDES Discharge without a Permit
  • CWA 404Permits for Dredge and Fill Material

Enforcement conclusions (1)

  • WALTON PLANTATION MASTER ASSOCIATION, INC.entered 2018-02-02

    Primary law: CWA

Timeline (2 milestones)

  • 2018-02-02Final Order Issued
  • 2018-03-29Enforcement Action Data Entered

Case metadata

EPA activity ID
3601394208
Case number
04-2018-5750
Lead agency
EPA
EPA region
04
Voluntary self-disclosure
No
Primary statute
NPDES Discharge without a Permit

Sourced verbatim from EPA ECHO Enforcement Case Report for case 04-2018-5750 . Bulk data: ICIS-FEC download summary.

This is legal information, not legal advice. Laws vary by jurisdiction and change frequently. Always verify current law with official sources and consult a licensed attorney in your jurisdiction for advice on your specific situation.