04-2018-2505Administrative - FormalClosedFY 2018· Region 04

EPA v. BOSS CONSTRUCTION SCHOOL, INC.

Final Order With Penalty

Case summary

3/29/18 - CONSENT AGREEMENT AND FINAL ORDER ISSUED, ASSESSING A PENALTY OF $1826. RESPONDENT SHALL MAKE PAYMENT WITHIN THIRTY DAYS. ORDER ALLEGES: BASED ON INFORMATION PROVIDED BY RESPONDENT TO THE EPA DATED OCTOBER 17, 2017 AND INFORMATION AVAILABLE IN THE EPA FEDERAL LEAD-BASED PROGRAM (FLPP) SYSTEM, THE EPA ALLEGES THAT RESPONDENT VIOLATED SECTION 402 AND 406 OF TSCA, BY FAILING TO TIMLEY PROVIDE REQUIRED TRAINING COURSE NOTIFICATIONS TO THE EPA AS FOLLOWS: PRE-TRAINING NOTIFICATION T534931, RENOVATOR-REFRESTHER, COURSE START DATE AND COMPLETION DATE OF JUNE 14, 2017: RESPONDENT'S TRAINING MANAGER FAILED TO PROVIDE THE PA WITH NOTIFICATION OF THIS LEAD-BASED PAINT ACTIVITIES COURSE AT LEAST 7 BUSINESS DAYS PRIOR TO THE START DATE OF THE COURSE, AS REQUIRED BY 40 CFR SECTION 745.225(c)(13)(i); PRE-TRAINING NOTIFICATION T52218, RENOVATOR-REFRESHER, COURSE START AND COMPLETION DATE OF MARCH 15, 2017: RESPONDENT'S TRAINING MANAGER FAILED TO PROVIDE THE EPA WITH NOTIFICATION OF THIS LEAD-BASED PAINT ACTIVITIES COURSE AT LEAST 7 BUSINESS DAYS PRIOR TO THE START DATE OF THE COURSE, AS REQUIRED BY 40 CFR SECTION 745.225(c)(13)(i); PRE-TRAINING NOTIFICATION T519162, RENOVATOR-INITIAL, COURSE START AND COMPLETION DATE OF FEBRUARY 22, 2017: RESPONDENT'S TRAINING MANAGER FAILED TO PROVIDE THE EPA WITH NOTIFICATION OF THIS LEAD-BASED PAINT ACTIVITIES COURSE AT LEAST 7 BUSINESS DAYS PRIOR TO THE START DATE OF THE COURSE, AS REQUIRED BY 40 CFR SECTION 745.225(c)(13)(i); PRE-TRAINING NOTIFICATION T519162, RENOVATOR-INITIAL, COURSE START AND COMPLETION DATE OF FEBRUARY 22, 2017: RESPONDENT'S TRAINING MANAGER FAILED TO PROVIDE THE EPA WITH NOTIFICATION OF THIS LEAD-BASED PAINT ACTIVITIES COURSE AT LEAST 7 BUSINESS DAYS PRIOR TO THE START DATE OF THE COURSE, AS REQUIRED BY 40 CFR SECTION 745.225(c)(13)(i); PRE-TRAINING NOTIFICATION T509389, RENOVATOR-INITIAL, COURSE START AND COMPLETION DATE OF DECEMBER 14, 2016: RESPONDENT'S TRAINING MANAGER FAILED TO PROVIDE THE EPA WITH NOTIFICATION OF THIS LEAD-BASED PAINT ACTIVITIES COURSE AT LEAST 7 BUSINESS DAYS PRIOR TO THE START DATE OF THE COURSE, AS REQUIRED BY 40 CFR SECTION 745.225(c)(13)(i);

Defendants (1)

  • BOSS CONSTRUCTION SCHOOL, INC.Named in complaintNamed in settlement

Facilities (1)

  • BOSS CONSTRUCTION SCHOOL, INC.

    1111 KANE CONCOURSE, SUITE 610, BAY HARBOR ISLANDS, FL, 33154

    Registry ID: 110070226071

Statutes cited

  • TSCA 406BLead: Pre-Renovation Education Rule
  • TSCA 402CLead: RRP

Enforcement conclusions (1)

  • BOSS CONSTRUCTION SCHOOL, INC.entered 2018-03-29

    Primary law: TSCA

    Federal penalty: $1,826

Timeline (4 milestones)

  • 2018-03-29Final Order Issued
  • 2018-03-29Complaint Filed/Proposed Order
  • 2018-04-06Enforcement Action Data Entered
  • 2018-04-26Enforcement Action Closed

Case metadata

EPA activity ID
3601402262
Case number
04-2018-2505
Lead agency
EPA
EPA region
04
Voluntary self-disclosure
No
Primary statute
Lead: Pre-Renovation Education Rule