Skip to main content
04-2017-8007Administrative - FormalClosedFY 2017· Region 04

EPA v. PMC ORGANOMETALLIX, INC.

Final Order With Penalty

Case summary

3/9/17 - CONSENT AGREEMENT AND FINAL ORDER ISSUED, ASSESSING A PENALTY OF 48,942. RESPONDENT SHALL MAKE PAYMENT WITHIN THIRTY DAYS. ORDER ALLEGES: BASED ON EPA'S COMPLIANCE MONITORING INVESTIGATION, THE EPA ALLEGES THAT THE RESPONDENT VIOLATED THE CODIFIED RULES GOVERNING THE ACT'S CHEMICAL ACCIDENT PREVENTION PROCEDURES, BECAUSE RESPONDENT DID NOT ADEQUATELY IMPLEMENT PROVISIONS OF 40 CFR PART 68 WHEN IT: ORDER ALLEGES: FAILED TO DOCUMENT THE NAMES OR POSITIONS OF PEOPLE AND DEFINE THE LINES AUTHORITY THROUGH AN ORGANIZATION CHART OR SIMILAR DOCUMENT, WHEN RESPONSIBILITY FOR IMPLEMENTING INDIVIDUAL REQUIREMENTS OF THE RMP IS ASSIGNED TO PERSONS OTHER THAN THE PERSONS IDENTIFIED UNDER PARAGRAPH (b) OF THE SECTION AS REQUIRED BY 40 CFR SECTION 68.15(c); FAILED TO INCLUDE PIPING AND INSTRUMENT DIAGRAMS PERTAINING TO THE EQUIPMENT IN THE PROCESS IN ITS PROCESS SAFETY INFORMATION AS REQUIRED BY 40 CFR SECTION 68.75(d)(1)(ii); AND FAILED TO CORRECT INFORMATION IN SECTION 68.65 BEFORE FURTHER USE OR IN A SAFE AND TIMELY MANNER WHEN NECESSARY MEANS ARE TAKEN TO ASSURE SAFE OPERATION AS REQUIRED BY 40 CFR SECTION 68.73(e).

Defendants (1)

  • PMC ORGANOMETALLIX, INC.Named in complaintNamed in settlement

Facilities (1)

  • PMC ORGANOMETALLIX INC

    13755-B HWY 43 N, AXIS, AL, 36505

    Registry ID: 110067013467

Statutes cited

  • CAA 112[R][7]Prevention of Accidental Release/Risk Management Plans (RMPs)

Enforcement conclusions (1)

  • PMC ORGANOMETALLIX, INC.entered 2017-03-09

    Primary law: CAA

    Federal penalty: $48,942

Timeline (4 milestones)

  • 2017-03-09Complaint Filed/Proposed Order
  • 2017-03-09Final Order Issued
  • 2017-03-23Enforcement Action Data Entered
  • 2017-05-02Enforcement Action Closed

Case metadata

EPA activity ID
3600987824
Case number
04-2017-8007
Lead agency
EPA
EPA region
04
Voluntary self-disclosure
No
Primary statute
Prevention of Accidental Release/Risk Management Plans (RMPs)

Sourced verbatim from EPA ECHO Enforcement Case Report for case 04-2017-8007 . Bulk data: ICIS-FEC download summary.

This is legal information, not legal advice. Laws vary by jurisdiction and change frequently. Always verify current law with official sources and consult a licensed attorney in your jurisdiction for advice on your specific situation.