EPA v. GEORGIA DEPARTMENT OF TRANSPORTAITON (GDOT) AUGUSTA - I-20 & I-520 INTERCHANGE PROJECT
Final Order With Penalty
Case summary
9/13/2011 - CONSENT AGREEMENT AND FINAL ORDER ISSUED, ASSESSING A PENALTY OF $177,500. RESPONDENT SHALL MAKE PAYMENT WITHIN THIRTY DAYS. ORDER ALLEGES: AT NO TIME DURING THE DISCHARGE OF DREDGED AND/OR FILL MATERIAL IMPACTING 1,478 LINEAR FEET AT THE DISCHARGE AREAS, FROM ON OR ABOUT JUNE 1, 2007, TO THE PRESENT, DID THE RESPONDENT POSSESS A PERMIT UNDER SECTION 404 OF THE CWA, AUTHORIZING SUCH STREAM ACTIVITIES PERFORMED BY RESPONDENT.
Defendants (1)
- GEORGIA DEPARTMENT OF TRANSPORTAITON (GDOT) AUGUSTNamed in complaintNamed in settlement
Facilities (1)
WETLANDS - GEORGIA DEPARTMENT OF TRANSPORTATION (NH-IM-520-1(15), NH-IM-20-2(145
I-20 AT I-520, AUGUSTA, GA, 30909
Registry ID: 110044218726
Statutes cited
- CWA 404 — Permits for Dredge and Fill Material
Enforcement conclusions (1)
GEORGIA DEPARTMENT OF TRANSPORTAITON (GDOT) AUGUSTA - I-20 & I-520 INTERCHANGE PROJECTentered 2011-09-13
Primary law: CWA
Federal penalty: $177,500
Timeline (4 milestones)
- 2011-09-13Final Order Issued
- 2011-09-13Complaint Filed/Proposed Order
- 2011-09-15Enforcement Action Data Entered
- 2011-10-25Enforcement Action Closed
Case metadata
- EPA activity ID
- 2600053487
- Case number
- 04-2011-5509
- Lead agency
- EPA
- EPA region
- 04
- Voluntary self-disclosure
- No
- Primary statute
- Permits for Dredge and Fill Material