04-2011-1519Administrative - FormalClosedFY 2011· Region 04

EPA v. MORGAN CONSTRUCTION COMPANY, INC. (FORMER GAS STATION)

Final Order With Penalty

Case summary

7/20/2011 - CONSENT AGREEMENT AND FINAL ORDER ISSUED, ASSESSING A PENALTY OF $6,610. RESPONDENT SHALL MAKE PAYMENT WITHIN THIRTY DAYS. ORDER ALLEGES: RESPONDENT VIOLATE SECTION 112 OF THE CAA, 42 U.S.C. SECTION 61.145(b)BY FAILING TO PROVIDE A WRITTEN NOTICE OF INTENTION TO DEMOLISH THE FACILITY PRIOR TO THE INITIATION OF DEMOLITION ACTIVITIES.

Defendants (1)

  • MORGAN CONSTRUCTION COMPANY, INC.Named in complaintNamed in settlement

Facilities (1)

  • FORMER GAS STATION

    887 BATTLEFIELD PKWY., FORT OGLETHORPE, GA, 30742

    Registry ID: 110043464300

Statutes cited

  • CAA 112BAsbestos

Enforcement conclusions (1)

  • MORGAN CONSTRUCTION COMPANY, INC.entered 2011-07-20

    Primary law: CAA

    Federal penalty: $6,610

Timeline (4 milestones)

  • 2011-07-20Final Order Issued
  • 2011-07-20Complaint Filed/Proposed Order
  • 2011-08-11Enforcement Action Data Entered
  • 2011-08-15Enforcement Action Closed

Case metadata

EPA activity ID
2600042955
Case number
04-2011-1519
Lead agency
EPA
EPA region
04
Voluntary self-disclosure
No
Primary statute
Asbestos