EPA v. RACETRAC PETROLEUM, INC.
Final Order With Penalty
Case summary
1/26/2010 - CONSENT AGREEMENT AND FINAL ORDER ISSUED, ASSESSING A PENALTY OF $24,300. RESPONDENT SHALL MAKE PAYMENT WITHIN THIRTY DAYS. ORDER ALLEGES: COMMENCING ON OR ABOUT AUGUST 1, 2009, RESPONDENT, OR THOSE ACTING ON BEHALF OF RESPONDENT, DISCHARGED DREDGED AND/OR FILL MATERIAL INTO WETLANDS ON THE SITE USING EARTH MOVING MACHINERY, DURING UNAUTHORIZED ACTIVITIES ASSOCIATED WITH THE CLEARING AND FILLING OF WETLANDS FOR COMMERCIAL DEVELOPMENT. AT NO TIME DURING THE DISCHARGE OF DREDGED AND/OR FILL MATERIAL AT THE DISCHARGE AREA BEGINNING ON AUGUST 9, 2009, DID THE RESPONDENT POSSESS A PERMIT UNDER SECTION 404 OF THE CWA.
Defendants (1)
- RACETRAC PETROLEUM, INC.Named in complaintNamed in settlement
Facilities (1)
WETLANDS - RACETRAC - MERRILL RD
8240 MERRILL RD, JACKSONVILLE, FL, 32277
Registry ID: 110039023936
Statutes cited
- CWA 404 — Permits for Dredge and Fill Material
Enforcement conclusions (1)
RACETRAC PETROLEUM, INC.entered 2010-01-26
Primary law: CWA
Federal penalty: $24,300
Timeline (4 milestones)
- 2010-01-26Complaint Filed/Proposed Order
- 2010-01-26Final Order Issued
- 2010-02-17Enforcement Action Data Entered
- 2010-02-23Enforcement Action Closed
Case metadata
- EPA activity ID
- 1800077171
- Case number
- 04-2010-5500
- Lead agency
- EPA
- EPA region
- 04
- Voluntary self-disclosure
- No
- Primary statute
- Permits for Dredge and Fill Material
Sourced verbatim from EPA ECHO Enforcement Case Report for case 04-2010-5500 . Bulk data: ICIS-FEC download summary.
This is legal information, not legal advice. Laws vary by jurisdiction and change frequently. Always verify current law with official sources and consult a licensed attorney in your jurisdiction for advice on your specific situation.