04-2010-1518Administrative - FormalClosedFY 2010· Region 04

EPA v. BRAVO FOOD GROUP, LLC / VARIETY CONSTRUCTION, INC.

Final Order With Penalty

Case summary

2/1/11 - CONSENT AGMT AND FINAL ORDER ISSUED, ASSESSING A PENALTY OF $6,374 WHICH SHALL BE PAID BY VARLEY CONSTRUCTION, INC., PURSUANT TO A SEPARATE AGMT BETWEEN THE RESPONDENTS, WITHIN 30 DAYS FROM THE EFFECTIVE DATE OF THIS CAFO. IN THE EVENT THAT VARLEY CONSTRUCTION, INC., FAILED TO PAY THE PENALTY AS REQUIRED IN THIS CAFO, BRAVO FOOD GROUP, LLC., SHALL PAY THE PENALTY WITHIN 30 DAYS AFTER RECEIPT OF A WRITTEN DEMAND FOR PAYMENT FROM EPA.

Defendants (2)

  • BRAVO FOOD GROUP, LLCNamed in complaintNamed in settlement
  • VARLEY CONSTRUCTION, INC.Named in complaintNamed in settlement

Facilities (1)

  • TACO BELL

    302 MALL BLVD., SAVANNAH, GA, 31402

    Registry ID: 110040058610

Statutes cited

  • CAA 112BAsbestos

Enforcement conclusions (1)

  • BRAVO FOOD GROUP, LLC / VARIETY CONSTRUCTION, INC.entered 2011-02-01

    Primary law: CAA

    Federal penalty: $6,374

Timeline (4 milestones)

  • 2011-02-01Final Order Issued
  • 2011-02-01Complaint Filed/Proposed Order
  • 2011-02-08Enforcement Action Data Entered
  • 2011-02-17Enforcement Action Closed

Case metadata

EPA activity ID
2200043985
Case number
04-2010-1518
Lead agency
EPA
EPA region
04
Voluntary self-disclosure
No
Primary statute
Asbestos