10/27/09 - CONSENT AGMT AND FINAL ORDER ISSUED, ASSESSING A PENALTY OF $10,000, DUE WITHIN 30 DAYS. EPA ALLEGES THAT SINCE THE COMPLIANCE DATE OF MARCH 24, 2003, RESPONDENT HAS BEEN IN VIOLATION OF 40 CFR 63.1506(m)(5), 63.1510(j)(4), AND 63.1512(o) BY NOT ESTABLISHING A TOTAL REACTIVE FLUX RATE FOR EACH GROUP 1 FURNACE.
Defendants (1)
- TENNESSEE ALUMINUM PROCESSORS, INC.Named in complaintNamed in settlement
Facilities (1)
TENNESSEE ALUMINUM PROCESSORS,INC.
7207 HOOVER MASON RD, MOUNT PLEASANT, TN, 38474
Registry ID: 110000375219
Statutes cited
- CAA 112 — Hazardous Air Pollutants
Enforcement conclusions (1)
TENNESSEE ALUMINUM PROCESSORS, INC.entered 2009-10-27
Primary law: CAA
Federal penalty: $10,000
Timeline (3 milestones)
- 2009-10-27Complaint Filed/Proposed Order
- 2009-10-27Final Order Issued
- 2009-12-21Enforcement Action Data Entered
Case metadata
- EPA activity ID
- 1800067014
- Case number
- 04-2010-1506
- Lead agency
- EPA
- EPA region
- 04
- Voluntary self-disclosure
- No
- Primary statute
- Hazardous Air Pollutants
Sourced verbatim from EPA ECHO Enforcement Case Report for case 04-2010-1506 . Bulk data: ICIS-FEC download summary.
This is legal information, not legal advice. Laws vary by jurisdiction and change frequently. Always verify current law with official sources and consult a licensed attorney in your jurisdiction for advice on your specific situation.