EPA v. B & M CONSTRUCTION
Final Order With Penalty
Case summary
9/14/09 - CONSENT AGMT AND FINAL ORDER ISSUED, ASSESSING A PENALTY OF $5,000 DUE WITHIN 30 DAYS. ALLEGATIONS: ON OR AFTER FEB 6, 2009, RESPONDENT DEMOLISHED A FACILITY LOCTEDAT 5220 SOUTH COBB DRIVE, SE, SMYRNA, GA 30080. RESPONDENT VIOLATED CAA SEC 112 AND 40 CFR 61.145(a) BY FAILING TO PROVIDE WRITTEN NOTICE OF INTENTION TO DEMOLISH THE FACILITY PRIOR TO THE INITIATION OF DEMOLITION ACTIVITIES.
Defendants (1)
- B&M CONSTRUCTION (SB )Named in complaintNamed in settlement
Facilities (1)
BP OIL CO
5220 SOUTH COBB DRIVE, SMYRNA, GA, 30080
Registry ID: 110005692731
Statutes cited
- CAA 112B — Asbestos
Enforcement conclusions (1)
B & M CONSTRUCTIONentered 2009-09-14
Primary law: CAA
Federal penalty: $5,000
Timeline (4 milestones)
- 2009-09-14Complaint Filed/Proposed Order
- 2009-09-14Final Order Issued
- 2009-09-17Enforcement Action Data Entered
- 2009-10-14Enforcement Action Closed
Case metadata
- EPA activity ID
- 1800023113
- Case number
- 04-2009-1519
- Lead agency
- EPA
- EPA region
- 04
- Voluntary self-disclosure
- No
- Primary statute
- Asbestos
Sourced verbatim from EPA ECHO Enforcement Case Report for case 04-2009-1519 . Bulk data: ICIS-FEC download summary.