EPA v. CAPSTONE PARTNERS, LLC (DOSS FERRY S/D)
Unilateral Administrative Order Without Adjudication
Case summary
9/9/2008 - ADMINISTRATIVE ORDER ISSUED. ORDER ALLEGES: RESPONDENT FAILED TO COMPLY WITH THE ADEM PERMIT REGULATIONS; AND ALSO FOR DISCHARGES NOT AUTHORIZED BY THE ADEM PERMIT REGULATIONS. IN VIOLATION OF CWA SECTIONS 301 & 402.
Defendants (2)
- CAPSTONE PARTNERS, LLC (SB)Named in settlement
- DOSS FERRY S/D
Facilities (1)
DOSS FERRY SUBDIVISION
OFF OF WARRIOR-KIMBERLY ROAD, BIRMINGHAM, AL, 35238
Registry ID: 110035839509
Statutes cited
- CWA 301/402 — NPDES Permit Violations
Enforcement conclusions (1)
CAPSTONE PARTNERS, LLCentered 2008-09-09
Primary law: CWA
Timeline (3 milestones)
- 2008-09-09Final Order Issued
- 2008-09-11Enforcement Action Data Entered
- 2009-01-01Enforcement Action Closed
Case metadata
- EPA activity ID
- 1400004178
- Case number
- 04-2008-4789
- Lead agency
- EPA
- EPA region
- 04
- Voluntary self-disclosure
- No
- Primary statute
- NPDES Permit Violations
Sourced verbatim from EPA ECHO Enforcement Case Report for case 04-2008-4789 . Bulk data: ICIS-FEC download summary.
This is legal information, not legal advice. Laws vary by jurisdiction and change frequently. Always verify current law with official sources and consult a licensed attorney in your jurisdiction for advice on your specific situation.