EPA v. PINELLAS CO. RESOURCE RECOVERY FACILITY
Unilateral Administrative Order Without Adjudication
Case summary
5/9/2008 - COMPLIANCE ORDER ISSUED. ORDER STATES: PURSUANT TO RULE 62-213.440(3)(a), F.A.C., THE COMPLIANCE CERTIFICATION IS DUE 60 DAYS AFTER THE END OF THE CALENDAR YEAR TO THE EPA. RESPONDENT WAS REQUIRED TO SUBMIT A COMPLIANCE CERTIFICATION FOR CALENDAR YEAR 2006 TO THE REGIONAL ADMINISTRATOR OF EPA REGION 4 BY MARCH 1, 2007. ACCORDING TO EPA RECORDS FOR COMPLIANCE CERTIFICATIONS, AS OF MAY 6, 2008, RESPONDENT HAD NOT SUBMITTED A COMPLIANCE CERTIFICATION TO THE REGIONAL ADMINISTRATOR OF EPA, REGION 4.
Defendants (1)
- PINELLAS CO. RESOURC RECOVERY FACILITY (SB)Named in settlement
Facilities (1)
PINELLAS CO. BOARD OF CO. COMMISSIONERS
3001 110TH AVE NORTH, SAINT PETERSBURG, FL, 337162002
Registry ID: 110002351838
Statutes cited
- CAA 114 — Record keeping, Inspection, Information Request
Enforcement conclusions (1)
PINELLAS CO. RESOURCE RECOVERY FACILITYentered 2008-05-09
Primary law: CAA
Timeline (2 milestones)
- 2008-05-09Final Order Issued
- 2008-06-24Enforcement Action Data Entered
Case metadata
- EPA activity ID
- 1000007297
- Case number
- 04-2008-1802
- Lead agency
- EPA
- EPA region
- 04
- Voluntary self-disclosure
- No
- Primary statute
- Record keeping, Inspection, Information Request