04-2008-1753Administrative - FormalFinal Order IssuedFY 2008· Region 04

EPA v. ALCOA EXTRUSIONS, INC.

Unilateral Administrative Order Without Adjudication

Case summary

12/10/2007 - COMPLIANCE ORDER ISSUED. ORDER ALLEGES: PURSUANT TO TULE 62-213.440(3), THE COMPLIANCE CERTIFICATION IS DUE 60 DAYS AFTER THE END OF THE CALENDAR YEAR TO THE EPA. RESPONDENT WAS REQUIRED TO SUBMIT A COMPLIANCE CERTIFICATION FOR CALENDAR YEAR 2006 TO THE REGIONAL ADMINISTRATOR OF EPA REGION 4 BY MARCH 1, 2007. ACCORDING TO EPA RECORDS FOR COMPLIANCE CERTIFICATIONS, AS OF DECEMBER 3, 2007, RESPONDENT HAD NOT SUBMITTED A COMPLIANCE CERTIFICATION TO THE REGIONAL ADMINISTRATOR OF EPA, REGION 4.

Defendants (1)

  • ALCOA EXTRUSIONS, INC.Named in settlement

Facilities (1)

  • GOLDEN ALUMINUM EXTRUSION, LLC PLANT CIT

    1650 ALUMAX CIRCLE, PLANT CITY, FL, 33567

    Registry ID: 110000364169

Statutes cited

  • CAA 114Record keeping, Inspection, Information Request

Enforcement conclusions (1)

  • ALCOA EXTRUSIONS, INC.entered 2007-12-10

    Primary law: CAA

Timeline (2 milestones)

  • 2007-12-10Final Order Issued
  • 2008-01-09Enforcement Action Data Entered

Case metadata

EPA activity ID
600077868
Case number
04-2008-1753
Lead agency
EPA
EPA region
04
Voluntary self-disclosure
No
Primary statute
Record keeping, Inspection, Information Request