04-2008-0768Administrative - FormalFinal Order IssuedFY 2008· Region 04

EPA v. PCUD-JOYLAN (EAST PASCO)

Unilateral Administrative Order Without Adjudication

Case summary

3/26/2008 - ADMINISTRATIVE ORDER ISSUED. ORDER ALLEGES: BASED ON INFORMATION AVAILABLE TO EPA, THE SYSTEM FAILED TO SUBMIT A STANDARD MONITORING PLAN, A SYSTEM SPECIFIC STUDY PLAN, OR A 40/30 CERTIFICATION TO THE EPA BY OCTOBER 1, 2007.

Defendants (1)

  • PCUD-JOYLAN (EAST PASCO)Named in settlement

Facilities (1)

  • PCUD-JOYLAN (EAST PASCO)

    DADE CITY, FL

    Registry ID: 110013164887

Statutes cited

  • SDWA 1433Intentional Acts

Enforcement conclusions (1)

  • PCUD-JOYLAN (EAST PASCO)entered 2008-03-26

    Primary law: SDWA

Timeline (2 milestones)

  • 2008-03-26Final Order Issued
  • 2008-03-31Enforcement Action Data Entered

Case metadata

EPA activity ID
600088242
Case number
04-2008-0768
Lead agency
EPA
EPA region
04
Voluntary self-disclosure
No
Primary statute
Intentional Acts

Sourced verbatim from EPA ECHO Enforcement Case Report for case 04-2008-0768 . Bulk data: ICIS-FEC download summary.

This is legal information, not legal advice. Laws vary by jurisdiction and change frequently. Always verify current law with official sources and consult a licensed attorney in your jurisdiction for advice on your specific situation.