EPA v. UNIVERSAL FOREST PRODUCTS
Unilateral Administrative Order Without Adjudication
Case summary
7/9/07 - COMPLIANCE ORDER ISSUED. ORDER REQUIRES: WITHIN 30 DAYS, PROVIDE A COPY OF THE STORM WATER POLLUTION PREVENTION PLAN ( THE PLAN ) DEVELOPED AND IMPLEMENTED IN ACCORDANCE WITH THE RENEWAL PERMIT ISSUED WITH AN EFFECTIVE DATE OF AUGUST 1, 2006, AND AN EXPIRATION DATE OF JULY 31, 2011. THE PLAN SHALL BE DEVELOPED AND IMPLEMENTED IN ACCORDANCE WITH THE RENEWAL PERMIT AND SHALL SPECIFICALLY COMPLY WITH THE REQUIREMENTS OF PART IV.B.1, PART IV.D.1, PART IV.D.2.a.(1), PART IV.D.2.a.(2), PART IV.D.2.b, PART IV.D.2.D, PART IV.D.2.e, PART IV.D.3.c, PART IV.D.3.d.(2)(, PART IV.D.3.g.(1), PART IV.D.3.i, AND PART VI.A.2 OF THIS PERMIT.
Defendants (1)
- UNIVERSAL FOREST PRODUCTS EASTERN DIV., INCNamed in settlement
Facilities (1)
UNIVERSAL FOREST PRODUCTS GEORGIA LIMITED PARTNERSHIP
560 INDUSTRIAL DRIVE, MOULTRIE, GA, 31768
Registry ID: 110000361162
Statutes cited
- CWA 301/402 — NPDES Permit Violations
Enforcement conclusions (1)
UNIVERSAL FOREST PRODUCTSentered 2007-07-09
Primary law: CWA
Timeline (3 milestones)
- 2007-07-09Final Order Issued
- 2007-08-17Enforcement Action Data Entered
- 2007-10-04Enforcement Action Closed
Case metadata
- EPA activity ID
- 600057202
- Case number
- 04-2007-4783
- Lead agency
- EPA
- EPA region
- 04
- Voluntary self-disclosure
- No
- Primary statute
- NPDES Permit Violations