EPA v. WALKER VENTURES, LLC (BLACK CREEK STATION)
Final Order With Penalty
Case summary
11/27/2007 - CONSENT AGREEMENT ISSUED, ASSESSING A PENALTY OF $15,000, DUE WITHIN 30 DAYS. ALLEGATIONS: RESPONDENT FAILED TO: PROVIDE A 35 FOOT BUFFER ON EITHER SIDE OF AN EXISTING STREAM ON THE PROPERTY; FAILED TO TAKE ALL REASONABLE STEPS TO PREVENT AND/OR MINIMMIZE, TO THE MAXIMUM EXTENT PRACTICABLE, ANY DISCHARGE BY NOT INSTALLING BMPs AND NOT MAINTAINING A BUFFER TO THE CREEK; FULLY IMPLMENT BMPs, INCLUDING MAINTAINING BMPs AND THE BUFFER; AND FAILED TO TAKE ALL REASONABLE STEPS, INCLUDING CESSATION OF CONSTRUCTION, BUILDING PRODUCTION OR OTHER ACTIVITIES, TO PREVENT/MINIMIZE IMPACTS TO THE CREEK BY NOT MAINTAINING THE BUFFER AND BMPs.
Defendants (2)
- WALKER VENTURES, INC.Named in complaintNamed in settlement
- BLACK CREEK STATIONNamed in complaintNamed in settlement
Facilities (1)
BLACK CREEK STATION
BLACK CREEK ROAD & NEW CASTLE ROAD, BIRMINGHAM, AL, 35223
Registry ID: 110030480478
Statutes cited
- CWA 301/402 — NPDES Permit Violations
Enforcement conclusions (1)
WALKER VENTURES, LLC (BLACK CREEK STATION)entered 2007-11-27
Primary law: CWA
Federal penalty: $15,000
Timeline (4 milestones)
- 2007-11-27Complaint Filed/Proposed Order
- 2007-11-27Final Order Issued
- 2007-11-29Enforcement Action Data Entered
- 2007-12-20Enforcement Action Closed
Case metadata
- EPA activity ID
- 600074448
- Case number
- 04-2007-4540
- Lead agency
- EPA
- EPA region
- 04
- Voluntary self-disclosure
- No
- Primary statute
- NPDES Permit Violations
Sourced verbatim from EPA ECHO Enforcement Case Report for case 04-2007-4540 . Bulk data: ICIS-FEC download summary.
This is legal information, not legal advice. Laws vary by jurisdiction and change frequently. Always verify current law with official sources and consult a licensed attorney in your jurisdiction for advice on your specific situation.