EPA v. SEAMAN TIMBER COMPANY, INC.
Final Order With Penalty
Case summary
5/22/2007 - CONSENT AGREEMENT AND FINAL ORDER ISSUED, ASSESSING A PENALTY OF $3,929. RESPONDENT SHALL MAKE PAYMENT WITHIN THIRTY DAYS. ON FEBRUARY 26, 2006, RESPONDENT HAD A RELEASE OF CREOSOTE ABOVE THE RQ AT THE FACILITY. RESPONDENT FAILED TO IMMEDIATELY NOTIFY THE NRC AS SOON AS RESPONDENT HAD KNOWLEDGE OF THE RELEASE OF CREOSOTE IN AN AMOUNT EQUAL TO OR GREATER THAN ITS RQ AT RESPONDENT'S FACILITY.
Defendants (1)
- SEAMAN TIMBER COMPANY, INC.Named in complaintNamed in settlement
Facilities (1)
SEAMAN TIMBER COMPANY, INC.
1051 HIGHWAY 25 SOUTH, MONTEVALLO, AL, 35115
Registry ID: 110070828368
Statutes cited
- CERCLA 103A — Notification of Hazardous Reportable Quantity Release
Enforcement conclusions (1)
SEAMAN TIMBER COMPANY, INC.entered 2007-05-22
Primary law: CERCLA
Federal penalty: $3,929 · SEP: $15,353
Timeline (3 milestones)
- 2007-05-22Final Order Issued
- 2007-05-22Complaint Filed/Proposed Order
- 2007-06-07Enforcement Action Data Entered
Case metadata
- EPA activity ID
- 600045493
- Case number
- 04-2007-2020
- Lead agency
- EPA
- EPA region
- 04
- Voluntary self-disclosure
- No
- Primary statute
- Notification of Hazardous Reportable Quantity Release
Sourced verbatim from EPA ECHO Enforcement Case Report for case 04-2007-2020 . Bulk data: ICIS-FEC download summary.
This is legal information, not legal advice. Laws vary by jurisdiction and change frequently. Always verify current law with official sources and consult a licensed attorney in your jurisdiction for advice on your specific situation.