EPA v. SYNTHRON CHEMICAL FIRE SITE
Final Order With Unspecified Cost Recovery
Case summary
3/29/06 - ADMINISTRATIVE SETTLEMENT AGREEMENT AND ORDER ON CONSENT FOR REMOVAL ACTION ISSUED. RESPONDENT: SYNTHRON, INC. RESPONDENT ALSO AGREES TO PAY PAST RESPONSE COSTS. EPA WILL SEND RESPONDENT A BILL REQUIRING PAYMENT THAT INCLUDES A SCORPIOS REPORT, WHICH INCLUDES DIRECT AND INDIRECT COSTS INCURRED BY EPA AND ITS CONTRACTORS. RESPONDENT SHALL SUBMIT PAYMENT TO EPA WITHIN 30 DAYS OF ITS RECEIPT OF EPA'S BILL. RESPONDENT ALSO AGRESS TO PAY FUTURE RESPONSE COSTS.
Defendants (1)
- SYNTHRON, INC. (SB)Named in settlement
Facilities (1)
SYNTHRON INCORPORATED
305 AMHERST RD., MORGANTON, NC, 286559362
Registry ID: 110000351164
Statutes cited
- CERCLA 106A — Imminent & Substantial Endangerment Order
Enforcement conclusions (1)
SYNTHRON CHEMICAL FIRE SITEentered 2006-03-29
Primary law: CERCLA
Timeline (2 milestones)
- 2006-03-29Final Order Issued
- 2006-04-03Enforcement Action Data Entered
Case metadata
- EPA activity ID
- 173107
- Case number
- 04-2006-3759
- Lead agency
- EPA
- EPA region
- 04
- Voluntary self-disclosure
- No
- Primary statute
- Imminent & Substantial Endangerment Order
Sourced verbatim from EPA ECHO Enforcement Case Report for case 04-2006-3759 . Bulk data: ICIS-FEC download summary.
This is legal information, not legal advice. Laws vary by jurisdiction and change frequently. Always verify current law with official sources and consult a licensed attorney in your jurisdiction for advice on your specific situation.