Skip to main content
04-2005-4759Administrative - FormalClosedFY 2005· Region 04

EPA v. LANDCRAFT PROPERTIES, INC. (REEDY FALLS SUBDIVISION)

Unilateral Administrative Order Without Adjudication

Case summary

12/28/04 - COMPLIANCE ORDER ISSUED. VIOLATIONS: FAILURE TO PROPERLY MAINTAIN THE FOLLOWING EROSION AND SEDIMENT CONTROLS: SILT FENCING, SEDIMENT PONDS, STORM DRAIN INLET AN DOUTLET PROTECTION THROUGHOUT THE SITE. FAILURE TO PROPERLY STABILIZE LARGE AREAS OF THE SITE. FAILURE TO RETAIN RECORDS AT THE SITE. ORDER REQUIRES: RESPONDENT SHALL PROVIDE OPERATION AND MAINTENANCE BY REPAIRING SILT FENCING THROUGHOUT THE SITE AND INSTALLING PROTECTION AT STORM DRAIN INLETS THROUGHOUT THE SITE TO PREVENT SEDIMENT DISCHARGE OFF-SITE IN THE FUTURE, AND INITIATE STABILIZATION MEASURES ON PORTIONS OF THE SITE WHERE CONSTRUCTION ACTIVITIES HAVE TEMPORARILY OR PERMANENTLY CEASED WITHIN 7 DAYS. RESPONDENT SHALL CLEAN AND MAINTAIN ALL SEDIMENTATION PONDS WITHIN 7 DAYS BY IMPLEMENTING AT A MINIMUM THE FOLLOWING: REMOVING SEDIMENT FROM PONDS, PROVIDING ROCK PROTECTION AROUND RISERS IN SEDIMENTATION PONDS, PROVIDING INLET PIPE PROTECTION AND OUTFALL PROTECTION AT PONDS. RESOPNDENT SHALL MODIFY THE SWPPP WITHIN 7 DAYS. RESPONDENT MUST IMMEDIATELY INSTITUTE AN INSPECTION PROGRAM, IF ONE DOES NOT ALREADY EXIST, WHICH COMPLIES WITH PART IV.D.4 OF THE PERMIT, FOR ALL DISTURBED AREAS AND AREAS USED FOR STORAGE OF MATERIALS THAT ARE EXPOSED TO PRECIPITATION, ALL EROSION AND SOIL CONTROL MEASURES IDENTIFIED IN THE SWPPP, ALL DISCHARGE LOCATIONS, AND ALL VEHICLE ENTRY AND EXIT LOCATIONS WITHIN 24 HOURS AFTER ANY STORM EVENT GREATER THAT 0.5 INCHES OF RAIN OR GREATER. RESPONDENT SHALL SUBMIT WRITTEN CERTIFICATION TO EPA AND SCDHEC THAT AN INSPECTION PROGRAM HAS/HAD BEEN INSTITUTED OR A PROJECTED DATE FOR ITS IMPLEMENTATION AND THE REASONS FOR ANY DELAYS NOT LATER THAN 14 DAYS. RESPONDENT SHALL ENSURE THAT RECORDS OF ALL INSPECTIONS ARE KEPT IN ACCORDANCE WITH PART IV.D.4 OF THE PERMIT. RESPONDENT SHALL SUBMIT COPIES OF THE SWPPP AND ALL INSPECTION REPORTS TO EPA AND SCDHEC WITHIN 14 DAYS, BEGINNING AT THE START OF CONSTRUCTION TO PRESENT. RESPONDENT SHALL ALSO SUBMIT COPIES OF ALL INSPECTION REPORTS TO EPA FOR A PERIOD OF 3 MONTHS FROM RECEIPT OF THIS ORDER EVERY 30 DAYS FOLLOWING IMPLEMENTATION OF THE INSPECTION PROGRAM INSTITUTED IN ACCORDANCE WITH PARAGRAPH 37 OF THIS ORDER. RESPONDENT SHALL ALSO SUBMIT A COPY OF ALL ADDITIONAL INFORMATION REQUIRED FOR A SWPPP AS REQUIRED UNDER PART IV OF THE PERMIT. RESPONDENT SHALL PROVIDE WRITTEN CERTIFICATION WITHIN 20 DAYS TO BOTH EPA AND SCDHEC THAT THOSE REQUIREMENTS CONTAINED IN PARAGRAPHS 35 AND 36 HAVE BEEN COMPLETED AND THAT THE SWPPP HAS BEEN MODIFIED

Defendants (1)

  • LANDCRAFT PROPERTIES, INC.Named in settlement

Facilities (1)

  • REEDY FALLS SUBDIVISION

    STANDING SPRINGS ROAD @ FERGUSON ROAD, MAULDIN, SC, 29662

    Registry ID: 110017840443

Statutes cited

  • CWA 301/402NPDES Permit Violations

Enforcement conclusions (1)

  • LANDCRAFT PROPERTIES, INC. (REEDY FALLS SUBDIVISION)entered 2004-12-28

    Primary law: CWA

Timeline (3 milestones)

  • 2004-12-28Final Order Issued
  • 2005-01-04Enforcement Action Data Entered
  • 2007-01-01Enforcement Action Closed

Case metadata

EPA activity ID
137370
Case number
04-2005-4759
Lead agency
EPA
EPA region
04
Voluntary self-disclosure
No
Primary statute
NPDES Permit Violations

Sourced verbatim from EPA ECHO Enforcement Case Report for case 04-2005-4759 . Bulk data: ICIS-FEC download summary.

This is legal information, not legal advice. Laws vary by jurisdiction and change frequently. Always verify current law with official sources and consult a licensed attorney in your jurisdiction for advice on your specific situation.