EPA v. STARMET CMI (CAMECO CORP)
Final Order With Specified Cost Recovery
Case summary
9/9/05 - DE MINIMIS ORDER ISSUED. SETTLING PARTY: CAMECO CORPORATION. WITHIN 30 DAYS OF THE EFFECTIVE DATE OF THIS ORDER, RESPONDENT SHALL PAY TO THE EPA STARMET SPECIAL ACCOUNT (OU 5), $894,176. RESPONDENT'S PAYMENT INCLUDES: (A) $33,513 FOR PAST RESPONSE COSTS INCLURRED AT OR IN CONNECTION WITH THE SITE; (B) $461,310 IN PROJECTED FUTURE RESPONSE COSTS TO BE INCURRED AT OR IN CONNECTION WITH THE SITE; (C) INDIRECT COSTS OF $230,340; AND (D) A PREMIUM OF $169,013 TO COVER THE RISKS AND UNCERTAINTIES ASSOCIATED WITH THIS SETTLEMENT, INCLUDING BUT NOT LIMITED TO, THE RISK THAT TOTAL RESPONSE COSTS INCURRED OR TO BE INCURRED AT OR IN CONNECTION WITH THE SITE BY THE EPA HAZARDOUS SUBSTANCE SUPERFUND, OR BY ANY PRIVATE PARTY, WILL EXCEED THE ESTIMATED TOTAL RESPONSE COSTS UPON WHICH RESPONDENT'S PAYMENT IS BASED
Defendants (1)
- CAMECO CORPNamed in settlement
Facilities (1)
STARMET CMI
365 METAL DRIVE HIGHWAY 80, BARNWELL, SC, 29812
Registry ID: 110008553190
Statutes cited
- CERCLA 122G — Administrative De Minimis Settlement
Enforcement conclusions (1)
STARMET CMI (CAMECO CORP)entered 2005-09-09
Primary law: CERCLA
Timeline (2 milestones)
- 2005-09-09Final Order Issued
- 2005-09-28Enforcement Action Data Entered
Case metadata
- EPA activity ID
- 158716
- Case number
- 04-2005-3781
- Lead agency
- EPA
- EPA region
- 04
- Voluntary self-disclosure
- No
- Primary statute
- Administrative De Minimis Settlement
Sourced verbatim from EPA ECHO Enforcement Case Report for case 04-2005-3781 . Bulk data: ICIS-FEC download summary.
This is legal information, not legal advice. Laws vary by jurisdiction and change frequently. Always verify current law with official sources and consult a licensed attorney in your jurisdiction for advice on your specific situation.