EPA v. RAMEY, INC. (AUTUMN WOODS - PHASE 3)
Unilateral Administrative Order Without Adjudication
Case summary
7/29/04 - COMPLIANCE ORDER ISSUED. VIOLATIONS: FAILURE TO TAKE CORRECTIVE ACTION IMMEDIATELY TO CONTROL THE DISCHARGE OF SEDIMENTS; FAILURE TO MAINTAIN A RECORD OF THE EROSION AND SEDIMENT CONTROL SITE INSPECTIONS PRIOR TO APRIL 26, 2004; FAILURE TO ADEQUATELY INSTALL AND/OR MAINTAIN TEMPORARY OR PERMANENT MEASURES THROUGHOUT THE SITE TO CONTROL AND RETAIN SEDIMENT, INCLUDING SILT FENCING; CONSTRUCTION ENTRANCES AND EXITS; STORM INLET PROTECTION; DIVERSION DITCHES; OUTLET AND OUTFALL PROTECTION; LACK OF ADEQUATE GROUNDCOVER AROUND THE SLOPES AND SEDIMENTATION BASINS; INSTALLING AND CONNECTING STORM DRAIN INFRASTRUCTURE INTO PERMANENT OUTFALLS PRIOR TO SITE STABILIZATION INSTEAD OF CONNECTING TO TEMPORARY SEDIMENTATION BASINS; AND INADEQUATE OR LACK OF CONSTRUCTION OF SEDIMENTATION BASINS AND SILT TRAPS
Defendants (1)
- RAMEY, INC.Named in settlement
Facilities (1)
AUTUMN WOODS - PHASE 3
HIGHWAY 273, MT. HOLLY, NC, 28120
Registry ID: 110024275103
Statutes cited
- CWA 301/402 — NPDES Permit Violations
Enforcement conclusions (1)
RAMEY, INC. (AUTUMN WOODS - PHASE 3)entered 2004-07-29
Primary law: CWA
Timeline (3 milestones)
- 2004-07-29Final Order Issued
- 2004-08-03Enforcement Action Data Entered
- 2007-01-01Enforcement Action Closed
Case metadata
- EPA activity ID
- 124677
- Case number
- 04-2004-4802
- Lead agency
- EPA
- EPA region
- 04
- Voluntary self-disclosure
- No
- Primary statute
- NPDES Permit Violations