04-2004-1771Administrative - FormalClosedFY 2004· Region 04
EPA v. MISSISSIPPI POWER COMPANY - PLANT EATON
Withdrawn by Region/State
Case summary
3/3/04 - COMPLIANCE ORDER ISSUED. AS OF MARCH 2, 2004, RESPONDENT HAS NOT SUBMITTED THE COMPLIANCE CERTIFICATION FOR CALENDAR YEAR 2004 TO EPA.
Defendants (1)
- MISSISSIPPI POWER PLANT - PLANT EATONNamed in settlement
Facilities (1)
MISSISSIPPI POWER COMPANY, PLANT EATON
950 SOUTH GEORGE STREET, PETAL, MS, 39465
Registry ID: 110002224799
Statutes cited
- CAA 114 — Record keeping, Inspection, Information Request
Enforcement conclusions (1)
MISSISSIPPI POWER COMPANY - PLANT EATON (COMPLIANCE ORDER)entered 2004-03-03
Primary law: CAA
Timeline (3 milestones)
- 2004-03-03Final Order Issued
- 2004-03-23Enforcement Action Data Entered
- 2004-04-06Enforcement Action Closed
Case metadata
- EPA activity ID
- 113910
- Case number
- 04-2004-1771
- Lead agency
- EPA
- EPA region
- 04
- Voluntary self-disclosure
- No
- Primary statute
- Record keeping, Inspection, Information Request
Sourced verbatim from EPA ECHO Enforcement Case Report for case 04-2004-1771 . Bulk data: ICIS-FEC download summary.
This is legal information, not legal advice. Laws vary by jurisdiction and change frequently. Always verify current law with official sources and consult a licensed attorney in your jurisdiction for advice on your specific situation.