Skip to main content
04-2003-5758Administrative - FormalFinal Order IssuedFY 2003· Region 04

EPA v. Horizon Natural Resources (Interim Compliance Order)

Unilateral Administrative Order Without Adjudication

Case summary

1/13/03 -- FINDINGS OF VIOLATION AND INTERIM ORDER FOR COMPLIANCE ISSUED. ORDER REQUIRES RESPONDENT TO: (1) CEASE AND DESIST ACTIVITIES EXCEPT FOR STABILITIZATION; (2) SEEK AUTHORIZATION FROM THE HUNTINGTON DISTRICT ARMY CORPS OF ENGINEERS TO PERFORM INTERIM CORRECTIVE MEASURES AT THE SUNNY RIDGE MINE TRACT TO PREVENT A POTENTIAL FLOOD EVENT THAT WOULD IMPACT DOWNSTREAM RESIDENCES; (3) COORDINATE ALL EMERGENCY STABILIZATION AND PROTECTION MEASURES WITH EPA AND DSMRE BEFORE INITIATING WORK.

Defendants (1)

  • HORIZON NATURAL RESOURCESNamed in settlement

Facilities (2)

  • WETLANDS (HORIZON NATURAL RESOURCES MINING SITE 1)

    ADJ TO MEADE, SING, EMILY & ROCKHOUSE BRANCHES, PIKEVILLE, KY, 41501

    Registry ID: 110013693315

  • WETLANDS (HORIZON NATURAL RESOURCES MINING SITE 2)

    BLUEBERRY CREEK,BALL,SMITH & BILLY DOTSON BRANCHES, DEBORD, KY, 41214

    Registry ID: 110014416783

Statutes cited

  • CWA 404Permits for Dredge and Fill Material

Enforcement conclusions (1)

  • Horizon Natural Resources (Interim Compliance Ordeentered 2003-01-13

    Primary law: CWA

Timeline (2 milestones)

  • 2003-01-13Final Order Issued
  • 2003-04-18Enforcement Action Data Entered

Case metadata

EPA activity ID
95080
Case number
04-2003-5758
Lead agency
EPA
EPA region
04
Voluntary self-disclosure
No
Primary statute
Permits for Dredge and Fill Material

Sourced verbatim from EPA ECHO Enforcement Case Report for case 04-2003-5758 . Bulk data: ICIS-FEC download summary.

This is legal information, not legal advice. Laws vary by jurisdiction and change frequently. Always verify current law with official sources and consult a licensed attorney in your jurisdiction for advice on your specific situation.