Skip to main content
04-2003-4804Administrative - FormalClosedFY 2003· Region 04

EPA v. D. R. Horton, Inc. - Torrey (Remington Subd.)

Final Order No Penalty

Case summary

7/31/2003 - Compliance Order issued. Respondent failed to properly design, install and maintain temporary sedimentation pond #2, which is located in a tributary thence to Rocky Creek a navigable waters of the United States. [Part VI.D. & N] Failed to install erosion and sediment controls along stream bank at sedimentation pond #2 to prevent discharge of sediment into Rocky Creek a navigable watersof the U.S. [Part VI.D.& N.] Failed to properly install and maintain silt fencing around perimert of the construction site (failed to trench silt fencing and silt fences appeared to be filled to greater than 50% of its capacity). Sediment was observed in the wetlands 35 feet from construction site. [Part VI.D. & N.

Defendants (1)

  • D. R. Horton, Inc. - TorreyNamed in complaintNamed in settlement

Facilities (1)

  • REMINGTON SUBDIVISIION

    WEST GEORGIA ROAD AND ROCK CREEK ROAD, GREENVILLE, SC, 29602

    Registry ID: 110015773037

Statutes cited

  • CWA 308Information Request, Records, Entry
  • CWA 301/402NPDES Permit Violations

Enforcement conclusions (1)

  • D. R. Horton, Inc. - Torreyentered 2003-07-31

    Primary law: CWA

Timeline (4 milestones)

  • 2003-07-31Final Order Issued
  • 2003-08-06Enforcement Action Data Entered
  • 2003-12-16Amended Administrative Order
  • 2005-02-24Enforcement Action Closed

Case metadata

EPA activity ID
100729
Case number
04-2003-4804
Lead agency
EPA
EPA region
04
Voluntary self-disclosure
No
Primary statute
Information Request, Records, Entry

Sourced verbatim from EPA ECHO Enforcement Case Report for case 04-2003-4804 . Bulk data: ICIS-FEC download summary.