EPA v. Arahova Partners
Unilateral Administrative Order Without Adjudication
Case summary
AO issued 11/20/2002. Respondent failed to properly operate and maintain all facilities and systes of treatment and control (and related appurtenances) which are installed or used by the permitee to achieve compliance in accordance with Part II.C.1 of the Permit. Respondent failed to comply with Final Limitations and Controls specified for storm water discharged once disturbance has begun on the site and until completion of construction or development and the establishment of a permanent gound cover, in accordance with Part I.C.1 of the Permit. Respondent failed to provide the operation and maintenance necessary to operate the storm water controls at optimum efficiency in accordance with Part I.C.2 of the Permit. Respondent failed to keep records of inspections and have them available for authorized representatives in accordance with Part I.B.3 and Part II.D.5.b of the Permit. Respondent failed to keep a rain gauge on site to document rainfall quantity, as required by Part I.B.1 of the Permit
Defendants (1)
- Arahova PartnersNamed in complaintNamed in settlement
Facilities (1)
ARAHOVA PARTNERS
STATESVILLE ROAD, HUNTERSVILLE, NC, 28078
Registry ID: 110013693690
Statutes cited
- CWA 301/402 — NPDES Permit Violations
Enforcement conclusions (1)
Arahova Partnersentered 2002-11-20
Primary law: CWA
Timeline (3 milestones)
- 2002-11-20Final Order Issued
- 2002-12-17Enforcement Action Data Entered
- 2007-01-01Enforcement Action Closed
Case metadata
- EPA activity ID
- 89645
- Case number
- 04-2003-4763
- Lead agency
- EPA
- EPA region
- 04
- Primary statute
- NPDES Permit Violations
Sourced verbatim from EPA ECHO Enforcement Case Report for case 04-2003-4763 . Bulk data: ICIS-FEC download summary.
This is legal information, not legal advice. Laws vary by jurisdiction and change frequently. Always verify current law with official sources and consult a licensed attorney in your jurisdiction for advice on your specific situation.