EPA v. Anchor Glass Container
Final Order With Penalty
Case summary
CAFO issued 7/18/2003, assessing a penalty of $71,076. Respondent also agrees to complete a SEP. PCB Violations: Section 6(e) of TSCA, 15 U.S.C. ��2605, and the regulations found at 40 C.F.R. ��761.30(a)(1)(viii) provide that as of December 1, 1985, combustible materials must not be stored within a Polychlorinated Biphenyl (PCB) Transformer enclosure, within 5 meters of a transformer enclosure, or in unenclosed, within 5 meters of a PCB Transformer. In Substations 2 and 4, Anchor Glass had two PCB Transformers, General Electric (GE), serial numbers C856072, and G856237, in use, with combustible materials, stored within 5 meters of these PCB Transformers, violating 40 C.F.R. ��761.30(a)(1)(viii). Section 6(e) of TSCA, 15 U.S.C. ��2605, and the regulations found at 40 C.F.R. ��761.30(a)(1)(viii) provide that as of December 1, 1985, combustible materials must not be stored within a PCB Transformer enclosure, within 5 meters of a transformer enclosure, or in unenclosed, within 5 meters of a PCB Transformer. In #3A, #3B, #3C, #3D Boost Tank Room, and Substation 5, Anchor Glass had five PCB Transformers, TEW, T-42092, TEW, T-40638-2, TEW, T-40561-2, TEW, T-41727, and an Allis Chalmer, serial number 85451, in use, with combustible materials, stored within 5 meters of these PCB Transformers, violating 40 C.F.R. ��761.30(a)(1)(viii). Section 6(e) of TSCA, 15 U.S.C. ��2605, and the regulations found at 40 C.F.R. ��761.30(a)(1)(xii) provide that records of inspection and maintenance history shall be maintained at least 3 years after disposing of the transformer and shall be made available for inspection, upon request by EPA. Anchor Glass had two GE PCB Transformers, serial numbers G856237 and G856237, located in Substations 2 and 4. Anchor Glass failed to conduct visual inspections on these PCB Transformers at least once every three (3) months for leaks/spills as required in 40 C.F.R. ��761.30(a)(1)(ix) and failed to maintain inspection logs of the inspection findings for third quarter in calendar year 2002, violating 40 C.F.R. ��761.30(a)(1)(xii). Section 6(e) of TSCA, 15 U.S.C. ��2605, and the regulations found at 40 C.F.R. ��761.30(a)(1)(xii) provide that records of inspection and maintenance history shall be maintained at least 3 years after disposing of the transformer and shall be made available for inspection, upon request by EPA. Anchor Glass had two GE PCB Transformers, serial numbers G856237 and G856237, located in Substations 2 and 4. Anchor Glass failed to conduct visual inspections on these PCB Transformers at least once every three (3) months for leaks/spills as required in 40 C.F.R. ��761.30(a)(1)(ix) and failed to maintain inspection logs of the inspection findings for second quarter in calendar year 2002, violating 40 C.F.R. ��761.30(a)(1)(xii). Section 6(e) of TSCA, 15 U.S.C. ��2605, and the regulations found at 40 C.F.R. ��761.30(a)(1)(xii) provide that records of inspection and maintenance history shall be maintained at least 3 years after disposing of the transformer and shall be made available for inspection, upon request by EPA. Anchor Glass had two GE PCB Transformers, serial numbers G856237 and G856237, located in Substations 2 and 4. Anchor Glass failed to conduct visual inspections on these PCB Transformers at least once every three (3) months for leaks/spills as required in 40 C.F.R. ��761.30(a)(1)(ix) and failed to maintain inspection logs of the inspection findings for third quarter in calendar year 2001, violating 40 C.F.R. ��761.30(a)(1)(xii). Section 6(e) of TSCA, 15 U.S.C. ��2605, and the regulations found at 40 C.F.R. ��761.30(a)(1)(xii) provide that records of inspection and maintenance history shall be maintained at least 3 years after disposing of the transformer and shall be made available for inspection, upon request by EPA. Anchor Glass had two GE
Defendants (1)
- Anchor Glass ContainerNamed in complaintNamed in settlement
Facilities (1)
ANCHOR GLASS JACKSONVILLE PLAN
2121 HURON ST, JACKSONVILLE, FL, 32254
Registry ID: 110022424296
Statutes cited
- TSCA 6-PCBS — PCBS
Enforcement conclusions (1)
Anchor Glass Containerentered 2003-07-18
Primary law: TSCA
Federal penalty: $71,076 · SEP: $106,920
Timeline (4 milestones)
- 2003-07-18Complaint Filed/Proposed Order
- 2003-07-18Final Order Issued
- 2003-08-21Enforcement Action Data Entered
- 2004-09-22Enforcement Action Closed
Case metadata
- EPA activity ID
- 101747
- Case number
- 04-2003-2550
- Lead agency
- EPA
- EPA region
- 04
- Primary statute
- PCBS
Sourced verbatim from EPA ECHO Enforcement Case Report for case 04-2003-2550 . Bulk data: ICIS-FEC download summary.