EPA v. JIMWAL Development, L.L.C.
Final Order No Penalty
Case summary
1/13/03 - CONSENT AGREEMENT FOR COMPLIANCE ISSUED. EPA HAS DETERMINED THAT THE RESPONDENT AND/OR THOSE ACTING ON BEHALF OF OR WITH PERMISSION FROM THE RESPONDENT, DISCHARGED DREDGED AND/OR FILL MATERIAL INTO WATERS OF THE U.S. AND ADJACENT JURISDICTIONAL WETLANDS DURING MECHANICAL LAND CLEARING, ROAD CONSTRUCTION AND STORMWATER MANAGEMENT FACILITY CONSTRUCTION AND THE DISCHARGE AREA. THIS ORDER PERTAINS TO AN UNNAMED TRIBUTARY OF IVY CREEK AND ADJACENT WETLANDS, WHICH IS TRIBUTARY TO SUWANEE CREEK AND THEN CHATTAHOOCHEE RIVER IN A DEVELOPMENT KNOWN AS BOGAN'S BRIDGE SUBDIVISION UNITS 2 AND 3, OFF OF EAST MADDOX ROAD, NEAR BUFORD, GWINNETT COUNTY, GA, NEAR 34 DEGREES 05.80' NORTH LATITUDE AND 83 DEGREES 58.31' WEST LONGITUDE. THE DIRECT DISCHARGES OCCURRED DURING CONSTRUCTION OF STORMWATER MGMT FACILITIES AND ROAD CROSSINGS. SECONDARY IMPACTS OCCURRED FROM A LACK OF ADEQUATE EROSION CONTROL IN SOME AREAS
Defendants (1)
- JIMWAL DEVELOPMENT, L.L.C.Named in complaintNamed in settlement
Facilities (1)
WETLANDS - BOGAN'S BRIDGE SUBDIVISION
OFF OF EAST MADDOX ROAD, BUFORD, GA, 30515
Registry ID: 110014420812
Statutes cited
- CWA 404 — Permits for Dredge and Fill Material
Enforcement conclusions (1)
JIMWAL Development, L.L.C.entered 2003-01-13
Primary law: CWA
Timeline (2 milestones)
- 2003-01-13Final Order Issued
- 2003-04-17Enforcement Action Data Entered
Case metadata
- EPA activity ID
- 95051
- Case number
- 04-2002-5765
- Lead agency
- EPA
- EPA region
- 04
- Primary statute
- Permits for Dredge and Fill Material
Sourced verbatim from EPA ECHO Enforcement Case Report for case 04-2002-5765 . Bulk data: ICIS-FEC download summary.
This is legal information, not legal advice. Laws vary by jurisdiction and change frequently. Always verify current law with official sources and consult a licensed attorney in your jurisdiction for advice on your specific situation.