EPA v. Triangle Pacific Corporation (Compliance Order)
Unilateral Administrative Order Without Adjudication
Case summary
'8/19/02 - Compliance order issued. Pursuant to the Respondent''s permit, Respondent was required to submit a compliance certificaiton for the year starting April 20, 2001 and ending April 19, 2002 to the Regional Administrator of EPA, Region 4, by June 20, 2002. According to EPA records for compliance certification, as of August 16, 2002, Respondent had not submitted a compliance certification to EPA.'
Defendants (1)
- Triangle Pacific CorporationNamed in complaintNamed in settlement
Facilities (1)
TRIANGLE PACIFIC CORPORATION
209 S. HILL STREET, MORRISTOWN, TN, 37814
Registry ID: 110000766001
Statutes cited
- CAA 114 — Record keeping, Inspection, Information Request
Enforcement conclusions (1)
Triangle Pacific Corporation (Compliance Order)entered 2002-08-19
Primary law: CAA
Timeline (2 milestones)
- 2002-08-19Final Order Issued
- 2002-10-05Enforcement Action Data Entered
Case metadata
- EPA activity ID
- 86566
- Case number
- 04-2002-1758
- Lead agency
- EPA
- EPA region
- 04
- Primary statute
- Record keeping, Inspection, Information Request