Skip to main content
04-1999-0321Administrative - FormalComplaint Filed/AO IssuedFY 1999· Region 04

EPA v. BOLIVAR COUNTY BOARD OF SUPERVISORS (MS)

Case summary

DURING THE SUMMER OF 1994, RESPONDENT DIRECTED BOLIVAR COUNTY EMPLOYEES IN THE CONSTRUCTION OF A TEMPORARY DAM IMMEDIATELY UPSTREAM OF THE EXISTING DAM ON LAKE BELUAH. THE EMPLOYEES USED TRACK HOES TO PLACE APPROX. 250 CUBIC YARDS OF FILL MATERIAL IMMEDIATELY BELOW THE LAKE BELUAH DAM. THESE ACTIONS WERE CONDUCTED AS PART OF AN EFFORT TO PREVENT LAKE BELUAH FROM DRAINING WHILE PERMANENT REPAIRS WERE ENACTED. HOWEVER, THESE EFFORTS HAVE MAINTAINED AN ABOVE AVERAGE WATER LEVEL IN THE LAKE RESULTING IN TREE MORTALITY ON VARIOUS ADJACENT LANDOWNERS PROPERTIES.

Defendants (1)

  • BOLIVAR COUNTY BOARD OF SUPERVISORS (MS)Named in complaint

Statutes cited

  • CWA 404Permits for Dredge and Fill Material

Timeline (2 milestones)

  • 1998-10-27Complaint Filed/Proposed Order
  • 1999-07-14Enforcement Action Data Entered

Case metadata

EPA activity ID
23198
Case number
04-1999-0321
Lead agency
EPA
HQ division
WAT
Branch
WAT
EPA region
04
Multimedia
No
Voluntary self-disclosure
No
Primary statute
Permits for Dredge and Fill Material

Sourced verbatim from EPA ECHO Enforcement Case Report for case 04-1999-0321 . Bulk data: ICIS-FEC download summary.

This is legal information, not legal advice. Laws vary by jurisdiction and change frequently. Always verify current law with official sources and consult a licensed attorney in your jurisdiction for advice on your specific situation.