Case summary
A DETERMINATION WAS MADE THAT THE PRESENCE OF HAZARDOUS WASTES AT FPL'S FORT MYERS PLANT FACILITY MAY PRESENT A SUBSTANTIAL HAZARD TO HUMAN HEALTH OR THE ENVIRONMENT. FPL IS ORDERED TO CONDUCT MONITORING, TESTING, ANALYSIS AND REPORTING TO ASCERTAIN THE NATURE AN DEXTENT OF SUCH HAZARD.
Defendants (1)
- FLORIDA POWER AND LIGHT COMPANYNamed in complaintNamed in settlement
Facilities (2)
FORT MYERS POWER PLANT
10650 SR 80, FORT MYERS, FL, 33905
Registry ID: 110000365248
FORT MYERS POWER PLANT
10650 SR 80, FORT MYERS, FL, 33905
Registry ID: 110000365248
Statutes cited
- RCRA 3013 — Monitoring, Analysis, Testing
Enforcement conclusions (1)
FLORIDA POWER AND LIGHT COMPANYentered 1998-03-03
Primary law: RCRA
Timeline (2 milestones)
- 1998-03-03Final Order Issued
- 1998-03-24Enforcement Action Data Entered
Case metadata
- EPA activity ID
- 22478
- Case number
- 04-1998-0108
- Lead agency
- EPA
- HQ division
- RCR
- Branch
- CER
- EPA region
- 04
- Multimedia
- No
- Voluntary self-disclosure
- No
- Primary statute
- Monitoring, Analysis, Testing
Sourced verbatim from EPA ECHO Enforcement Case Report for case 04-1998-0108 . Bulk data: ICIS-FEC download summary.
This is legal information, not legal advice. Laws vary by jurisdiction and change frequently. Always verify current law with official sources and consult a licensed attorney in your jurisdiction for advice on your specific situation.